Grid connection · England, United Kingdom

Stalbridge grid connection

Stalbridge grid connection is a grid connection in England, United Kingdom, with 4.13 MW of capacity, held by Nextenergy Solar Holdings VI Limited.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
Name in the sourceSTALBRIDGE grid connectionSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
LocationEngland (connects at Henstridge)SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
StatusOperating (connected)SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
HolderNextenergy Solar Holdings VI LimitedSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Attached toLand at Stalbridge Park (matched by shared name+coordinates+technology+capacity+company, 1.2 km away)Rare Context entity resolution · CC0 1.0 · checked 24 Oct 2026
Attached toHenstridge Primary (via a primary substation)SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Capacity4.13 MWSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
TechnologySolarSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Grid operatorSouthern Electric Power Distribution plcSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Connection date29 Mar 2017SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Voltage11 kVSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Coordinates50.9624, -2.3841SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026

Research on this grid connection and its holder.Who holds it up to the parent company, the project behind it and its connection date, and an introduction to the holder.

Request research

Latest events

Dated events about this grid connection and the records linked to it from official notices and registers, newest first. All recent changes.

  1. Commissioned: Land at Stalbridge Park
  2. Permit granted: Land at Stalbridge Park (planning authority Dorset, reference 2/2015/0898/FUL)
  3. Permit applied for: Land at Stalbridge Park (planning authority Dorset, reference 2/2015/0898/FUL)

How it compares

Stalbridge grid connection is the 1,813th-largest of 2,533 grid connections in England and the 2,820th-largest of 3,903 in the United Kingdom by capacity; its 4.13 MW is <0.1% of the 446,745 MW we hold for the United Kingdom. Ranks and totals cover the grid connections in our data that report their capacity, not every one in existence.

WithinRankTotalShare
England1,813th of 2,533319,370 MW<0.1%
United Kingdom2,820th of 3,903446,745 MW<0.1%
All grid connections in our data6,800th of 7,9281,372,494 MW<0.1%

Nearby

Within 50 km of this grid connection: 332 power plants (155 operating, 1,089 MW), 105 substations, 1 data center and 1 transmission line, measured from the coordinates in the facts above. The table shows the nearest 8, up to 3 per kind.

NameKindSizeStatusDistance
Henstridge PrimarySubstation——1.2 km
Land at Stalbridge ParkPower plant5 MWOperating1.2 km
Land at Bowden LanePower plant5 MWOperating3.7 km
Milborne Port Solar FarmPower plant4.2 MWOperating4.9 km
Milborne Port PrimarySubstation——5.4 km
West Stour PrimarySubstation——6.0 km
Data Vault - Bournemouth BCP01Data center——45 km
Hinkley Point C ConnectionTransmission line—Permitted49 km

Holder, grid operator and place

More from Nextenergy Solar Holdings VI Limited

Other grid connections in England

All 3831 grid connections in England, United Kingdom

Data on this page