Grid connection · England, United Kingdom

Solar 1.4 MW grid connection at Middleton Town Street

Solar 1.4 MW grid connection at Middleton Town Street is a grid connection in England, United Kingdom, with 1.4 MW of capacity, connected by Northern Powergrid (Yorkshire) plc.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationEngland (connects at Middleton Town Street)Northern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
StatusOperating (connected)Northern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
Attached toMiddleton Town Street (via a primary substation)Northern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
Capacity1.4 MWNorthern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
TechnologySolarNorthern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
Grid operatorNorthern Powergrid (Yorkshire) plcNorthern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
Queue date20 Jul 2023Northern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
Connection date6 Mar 2026Northern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
Voltage11 kVNorthern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
Coordinates53.7658, -1.5404Northern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026

Research on this grid connection and its holder.Who holds it up to the parent company, the project behind it and its connection date, and an introduction to the holder.

Request research

How it compares

Solar 1.4 MW grid connection at Middleton Town Street is the 2,348th-largest of 2,533 grid connections in England and the 3,640th-largest of 3,903 in the United Kingdom by capacity; its 1.4 MW is <0.1% of the 446,745 MW we hold for the United Kingdom. Ranks and totals cover the grid connections in our data that report their capacity, not every one in existence.

WithinRankTotalShare
England2,348th of 2,533319,370 MW<0.1%
United Kingdom3,640th of 3,903446,745 MW<0.1%
All grid connections in our data7,656th of 7,9281,372,494 MW<0.1%

Timeline

Dated facts about this grid connection from its sources, oldest first.

  1. Entered the connection queue
  2. Connected

Nearby

Within 50 km of this grid connection: 431 substations, 401 power plants (110 operating, 6,798 MW), 11 data centers and 1 transmission line, measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.

NameKindSizeStatusDistance
Leasowe RoadSubstation——1.3 km
Middleton Town StreetSubstation——1.6 km
Low RoadSubstation——2.0 km
Pollington Energy ParkPower plant53 MWCancelled2.3 km
Knostrop WWTW ADPower plant2.4 MWOperating2.9 km
GridJetData center——2.9 km
Skelton Grange – Energy Recovery FacilityPower plant49 MWUnder construction3.3 km
nLighten LeedsData center——12 km
HSBC Wakefield Data CentreData center——13 km

Grid operator and place

More from Northern Powergrid (Yorkshire) plc

Other grid connections in England

All 3831 grid connections in England, United Kingdom

Data on this page