Grid connection · England, United Kingdom

Port Office grid connection

Port Office grid connection is a planned grid connection in England, United Kingdom, with 2.2 MW of capacity, connected by Northern Powergrid (Yorkshire) plc.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationEngland (connects at King George Dock)Northern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
StatusPlanned (accepted to connect)Northern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
Attached toKing George Dock (via a primary substation)Northern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
Capacity2.2 MWNorthern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
TechnologySolarNorthern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
Grid operatorNorthern Powergrid (Yorkshire) plcNorthern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
Queue date5 Nov 2024Northern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
Voltage11 kVNorthern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
Coordinates53.7456, -0.3247Northern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026

Research on this grid connection and its grid operator.Who holds it up to the parent company, the project behind it and its connection date, and an introduction to the grid operator.

Request research

How it compares

Port Office grid connection is the 2,131st-largest of 2,533 grid connections in England and the 3,289th-largest of 3,903 in the United Kingdom by capacity; its 2.2 MW is <0.1% of the 446,745 MW we hold for the United Kingdom. Ranks and totals cover the grid connections in our data that report their capacity, not every one in existence.

WithinRankTotalShare
England2,131st of 2,533319,370 MW<0.1%
United Kingdom3,289th of 3,903446,745 MW<0.1%
All grid connections in our data7,295th of 7,9281,372,494 MW<0.1%

Nearby

Within 50 km of this grid connection: 299 power plants (75 operating, 3,609 MW), 122 substations, 2 transmission lines and 1 gas storage facility, measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.

NameKindSizeStatusDistance
Alfred Gelder StreetSubstation——0.5 km
Cornwall Street DirectSubstation——1.2 km
Energy Works (Hull)Power plant25 MWOperating1.5 km
Energy Works Hull - AD (Waste AD)Power plant3 MWOperating1.5 km
Energy Works Hull - Wind TurbinePower plant3 MWOperating1.5 km
Clarendon StreetSubstation——1.9 km
Continental Link Multi-Purpose InterconnectorTransmission line—Cancelled8.6 km
Aldbrough Hydrogen StorageGas storage facility—Planned17 km
North Humber to High MarnhamTransmission line—Planned48 km

Grid operator and place

More from Northern Powergrid (Yorkshire) plc

Other grid connections in England

All 3831 grid connections in England, United Kingdom