Substation · England, United Kingdom

Alfred Gelder Street

Alfred Gelder Street is a substation in England, United Kingdom, connected by Northern Powergrid (Yorkshire) plc.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationEnglandNorthern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
Grid operatorNorthern Powergrid (Yorkshire) plcNorthern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
Demand headroom7.45 MVANorthern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
Generation headroom2.89 MWNorthern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
Firm capacity24 MVANorthern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
LevelPrimaryNorthern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
Fed fromCreyke BeckNorthern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
Fed fromHull SouthNorthern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
Congestion (offtake)None (rag: Green)Northern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
Congestion (feed-in)None (rag: Green)Northern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
Voltage11 kVNorthern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
Coordinates53.7449, -0.3318Northern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026

Know more about this substation, or want an introduction to its grid operator? Ask us.

Nearby

Within 50 km of this substation: 304 power plants (78 operating, 3,621 MW), 262 grid connections (128 operating, 2,085 MW), 2 transmission lines and 1 CO2 emitter, measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.

NameKindSizeStatusDistance
Port Office grid connectionGrid connection2.2 MWPlanned0.5 km
Wind 6.9 MW grid connection at King George DockGrid connection6.9 MWPlanned0.5 km
Gas 25 MW grid connection at Cleveland Street Generation DirectGrid connection25 MWOperating1.6 km
Energy Works (Hull)Power plant25 MWOperating1.6 km
Energy Works Hull - AD (Waste AD)Power plant3 MWOperating1.6 km
Energy Works Hull - Wind TurbinePower plant3 MWOperating1.6 km
Continental Link Multi-Purpose InterconnectorTransmission line—Cancelled8.3 km
Aldbrough Hydrogen StorageCO2 emitter—Planned18 km
North Humber to High MarnhamTransmission line—Planned47 km