Grid connection · England, United Kingdom

Kimpton Wood Solar Farm grid connection

Kimpton Wood Solar Farm grid connection is a planned grid connection in England, United Kingdom, with 42.7 MW of capacity, held by Low Carbon UK Solar Investment Company Limited.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
Name in the sourceKIMPTON WOOD SOLAR FARM grid connectionSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
LocationEngland (connection site: BRAMLEY (THAT-AMES))SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
StatusPlanned (ACCEPTED TO CONNECT)SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
HolderLow Carbon UK Solar Investment Company LimitedSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Attached toPerham Down - Meadow Solar Farm & Battery Storage (method: coordinates+technology+capacity+company, distance km: 1.76)Rare Context entity resolution · CC0 1.0 · checked 24 Oct 2026
Capacity42.7 MWSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
TechnologySolarSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
TechnologyBattery storageSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Grid operatorSouthern Electric Power Distribution plcSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Queue date9 May 2023SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Connection date30 Nov 2025 (target energisation)SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Voltage132 kVSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Coordinates51.2398, -1.6055SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026

Know more about this grid connection, or want an introduction to its holder? Ask us.

How it compares

Kimpton Wood Solar Farm grid connection is the 725th-largest of 2,533 grid connections in England and the 1,119th-largest of 3,903 in the United Kingdom by capacity; its 42.7 MW is <0.1% of the 446,745 MW we hold for the United Kingdom. Ranks and totals cover the grid connections in our data that report their capacity, not every one in existence.

WithinRankTotalShare
England725th of 2,533319,370 MW<0.1%
United Kingdom1,119th of 3,903446,745 MW<0.1%
All grid connections in our data4,258th of 7,6161,281,251 MW<0.1%

Timeline

Dated facts about this grid connection from its sources, oldest first.

  1. Entered the connection queue
  2. Connected

Nearby

Within 50 km of this grid connection: 342 power plants (137 operating, 1,775 MW) and 197 substations, measured from the coordinates in the facts above. The table shows the nearest 6, up to 3 per kind.

NameKindSizeStatusDistance
South Park Solar FarmPower plant15 MWPermitted0.8 km
Perham Down - Meadow Solar Farm & Battery StoragePower plant49.9 MWPermitted1.8 km
Tidworth PrimarySubstation——3.6 km
Thruxton PrimarySubstation——3.7 km
Manor Farm (Thruxton)Power plant12.5 MWCancelled3.8 km
Park House PrimarySubstation——6.9 km

Holder, grid operator and place

More from Low Carbon UK Solar Investment Company Limited

Other grid connections in England

All 3831 grid connections in England, United Kingdom

Data on this page