Power plant · Test Valley, England, United Kingdom

Perham Down - Meadow Solar Farm & Battery Storage

Perham Down - Meadow Solar Farm & Battery Storage is a permitted power plant in Test Valley, England, United Kingdom, with 49.9 MW of capacity, operated by Low Carbon UK Solar Investment Co Limited.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationTest Valley (coordinates), EnglandDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
AddressMeadow Solar Farm, Se/O Perham Down, Andover, SP11 8PQDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
StatusPermitted (planning permission granted)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Permit date18 Nov 2022 (permit 21/01749/FULLN, Town and Country Planning Act, issued by Test Valley)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Application date9 Jun 2021 (ref. 21/01749/FULLN, Test Valley)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Decision date18 Nov 2022 (granted, ref. 21/01749/FULLN, Test Valley)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
OperatorLow Carbon UK Solar Investment Co LimitedDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Capacity49.9 MWDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
TechnologySolar PhotovoltaicsDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Area75.5 ha (solar site area)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Coordinates51.2255, -1.6160DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026

Know more about this power plant, or want an introduction to its operator? Ask us.

How it compares

Perham Down - Meadow Solar Farm & Battery Storage is the 514th-largest of 2,174 power plants planned, permitted or under construction in England and the 886th-largest of 3,222 in the United Kingdom by capacity; its 49.9 MW is <0.1% of the 300,661 MW of power plants planned, permitted or under construction we hold for the United Kingdom. It is not built yet, so it is ranked among the power plants planned, permitted or under construction in our data, apart from the ones running today. Ranks and totals cover the ones that report their capacity.

WithinRankTotalShare
England514th of 2,174186,088 MW<0.1%
United Kingdom886th of 3,222300,661 MW<0.1%
All power plants planned, permitted or under construction in our data1,966th of 6,455664,240 MW<0.1%

Nearby

Within 50 km of this power plant: 287 grid connections (159 operating, 1,748 MW) and 196 substations, measured from the coordinates in the facts above. The table shows the nearest 6, up to 3 per kind.

NameKindSizeStatusDistance
Kimpton Wood Solar Farm grid connectionGrid connection42.7 MWPlanned1.8 km
RY South Park Farm grid connectionGrid connection14.3 MWPlanned1.8 km
Thruxton PrimarySubstation——2.8 km
Lains Farm PV grid connectionGrid connection3.33 MWOperating3.0 km
Tidworth PrimarySubstation——3.5 km
Park House PrimarySubstation——5.2 km

Operator and place

Grid connections attached to this power plant

More from Low Carbon UK Solar Investment Co Limited

Other power plants in England

All 5809 power plants in England, United Kingdom