Broomfield Solar Farm grid connection

Broomfield Solar Farm grid connection is a planned grid connection in England, United Kingdom, with 20 MW of capacity, held by Low Carbon Solar Park Limited.

Map: where Broomfield Solar Farm grid connection lies
50.9888, -0.2937 on OpenStreetMap

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationEngland (connects at Bolney Grid 33kV)UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
StatusPlanned (accepted to connect)UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
HolderLow Carbon Solar Park LimitedUK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
Attached toBolney Grid 33kV (via a primary substation)UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
Capacity20 MWUK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
TechnologySolarUK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
Grid operatorSouth Eastern Power Networks plc (UK Power Networks, South East England licence area)UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
Queue date21 Sept 2021UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
Connection date18 Oct 2027 (target energisation)UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
Voltage33 kVUK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
Coordinates50.9888, -0.2937UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026

Research on this grid connection and its holder.Who holds it up to the parent company, the project behind it and its connection date, and an introduction to the holder.

How it compares

Broomfield Solar Farm grid connection is the 1,321st-largest of 3,539 grid connections in England and the 1,923rd-largest of 4,870 in the United Kingdom by capacity; its 20 MW is <0.1% of the 467,981 MW we hold for the United Kingdom. Ranks and totals cover the grid connections in our data that report their capacity, not every one in existence.

WithinRankTotalShare
England1,321st of 3,539341,715 MW<0.1%
United Kingdom1,923rd of 4,870467,981 MW<0.1%
All grid connections in our data5,304th of 8,6181,355,288 MW<0.1%

Timeline

Dated facts about this grid connection from its sources, oldest first.

  1. Entered the connection queue
  2. Due to connect

Nearby

Within 50 km of this grid connection: 229 substations, 176 power plants (75 operating, 1,261 MW) and 22 data centers, measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.

NameKindSizeStatusDistance
Cobwood Solar Farm, Burnthouse Lane - Solar Farm & Battery StoragePower plant49.9 MWPermitted0.8 km
Kent Street, Cowfold - Battery Energy Storage SystemPower plant57 MWCancelled3.7 km
Cowfold 11kVSubstation——3.7 km
Bolney Grid 33kVSubstation——4.4 km
Bolney - Battery StoragePower plant200 MWPermitted4.4 km
Southwater 11kVSubstation——4.7 km
IBM HorshamData center——5.4 km
Digital Realty LGW15Data center——17 km
Digital Realty LGW16Data center——18 km

Holder, grid operator and place