Power plant · Horsham, England, United Kingdom

Cobwood Solar Farm, Burnthouse Lane - Solar Farm & Battery Storage

Cobwood Solar Farm, Burnthouse Lane - Solar Farm & Battery Storage is a permitted power plant in Horsham, England, United Kingdom, with 49.9 MW of capacity, operated by Low Carbon UK Solar.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationHorsham (coordinates), EnglandDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
AddressCobwood Solar Farm, Burnthouse Lane, Cowfold, Horsham, RH13 8DGDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
StatusPermitted (planning permission granted)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Permit date24 May 2024 (permit DC/23/2172, Town and Country Planning Act, issued by Horsham)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Application date29 Nov 2023 (reference DC/23/2172, planning authority Horsham)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Decision date24 May 2024 (granted, reference DC/23/2172, planning authority Horsham)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
OperatorLow Carbon UK SolarDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Capacity49.9 MWDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
TechnologySolar PhotovoltaicsDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Area73.3 ha (solar site area)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Coordinates50.9948, -0.2867DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026

Research on this power plant and its operator.Who owns it up to the parent company, its grid connection and planning status, and an introduction to the operator.

Request research

How it compares

Cobwood Solar Farm, Burnthouse Lane - Solar Farm & Battery Storage is the 514th-largest of 2,174 power plants planned, permitted or under construction in England and the 886th-largest of 3,222 in the United Kingdom by capacity; its 49.9 MW is <0.1% of the 300,661 MW of power plants planned, permitted or under construction we hold for the United Kingdom. It is not built yet, so it is ranked among the power plants planned, permitted or under construction in our data, apart from the ones running today. Ranks and totals cover the ones that report their capacity.

WithinRankTotalShare
England514th of 2,174186,088 MW<0.1%
United Kingdom886th of 3,222300,661 MW<0.1%
All power plants planned, permitted or under construction in our data1,966th of 6,455664,240 MW<0.1%

Nearby

Within 50 km of this power plant: 59 grid connections (37 operating, 216 MW), 51 substations and 21 data centers, measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.

NameKindSizeStatusDistance
IBM HorshamData center——5.4 km
Five Oaks PrimarySubstation——11 km
Solar 3.905 MW grid connection at Five Oaks Farm PVGrid connection3.91 MWOperating12 km
Billingshurst PrimarySubstation——12 km
Malham Farm Solar & Storage grid connectionGrid connection20 MWPlanned15 km
Digital Realty LGW15Data center——17 km
Digital Realty LGW16Data center——17 km
Plaistow PrimarySubstation——19 km
Solar 4.75 MW grid connection at PlaistowGrid connection4.75 MWOperating20 km

Operator and place

More from Low Carbon UK Solar

Other power plants in England

All 5809 power plants in England, United Kingdom