Bolney - Battery Storage

Bolney - Battery Storage is a permitted power plant in Mid Sussex, England, United Kingdom, with 200 MW of capacity, operated by Elements Green.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationMid Sussex (coordinates), EnglandDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
AddressLand east of Wineham Lane, Wineham, Henfield, BN5 9AYDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
StatusPermitted (planning permission granted)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Permit date5 Sept 2024 (permit DM/21/2276, Town and Country Planning Act, issued by Horsham)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Application date22 Jun 2021 (reference DM/21/2276, planning authority Horsham)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Decision date5 Sept 2024 (granted, reference DM/21/2276, planning authority Horsham)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
OperatorElements GreenDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Capacity200 MWDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
TechnologyBattery (stand-alone storage)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Coordinates50.9699, -0.2385DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026

Research on this power plant and its operator.Who owns it up to the parent company, its grid connection and planning status, and an introduction to the operator.

Request research

Latest events

Dated events about this power plant from official notices and registers, newest first. All recent changes.

  1. Permit granted (planning authority Horsham, reference DM/21/2276)
  2. Permit applied for (planning authority Horsham, reference DM/21/2276)

How it compares

Bolney - Battery Storage is the 177th-largest of 2,174 power plants planned, permitted or under construction in England and the 279th-largest of 3,222 in the United Kingdom by capacity; its 200 MW is <0.1% of the 300,461 MW of power plants planned, permitted or under construction we hold for the United Kingdom. It is not built yet, so it is ranked among the power plants planned, permitted or under construction in our data, apart from the ones running today. Ranks and totals cover the ones that report their capacity.

WithinRankTotalShare
England177th of 2,174185,888 MW0.11%
United Kingdom279th of 3,222300,461 MW<0.1%
All power plants planned, permitted or under construction in our data741st of 6,455664,040 MW<0.1%

Nearby

Within 50 km of this power plant: 40 grid connections (29 operating, 160 MW), 33 substations and 16 data centers, measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.

NameKindSizeStatusDistance
IBM HorshamData center——9.7 km
Five Oaks PrimarySubstation——16 km
Solar 3.905 MW grid connection at Five Oaks Farm PVGrid connection3.91 MWOperating16 km
Billingshurst PrimarySubstation——17 km
Digital Realty LGW15Data center——18 km
Digital Realty LGW16Data center——18 km
Malham Farm Solar & Storage grid connectionGrid connection20 MWPlanned20 km
Plaistow PrimarySubstation——24 km
Solar 4.75 MW grid connection at PlaistowGrid connection4.75 MWOperating24 km