Kent Street, Cowfold - Battery Energy Storage System is a cancelled power plant in Horsham, England, United Kingdom, with 57 MW of capacity, operated by Bolney Green Energy Hub and Enso Energy Limited.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationHorsham (coordinates), EnglandDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
AddressW/O Kent Street, Cowfold, Horsham, RH13 8BBDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
StatusCancelled (planning permission refused)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Application date26 Jan 2024 (reference DC/24/0054, planning authority Horsham)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Decision date19 Jul 2024 (refused, reference DC/24/0054, planning authority Horsham)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
OperatorBolney Green Energy Hub (Enso Energy / Bolney Green Energy Hub, applicant)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
OperatorEnso Energy Limited (Enso Energy / Bolney Green Energy Hub, applicant)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Capacity57 MWDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
TechnologyBattery (stand-alone storage)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Coordinates50.9832, -0.2422DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026

Research on this power plant and its operator.Who owns it up to the parent company, its grid connection and planning status, and an introduction to the operator.

Request research

Latest events

Dated events about this power plant from official notices and registers, newest first. All recent changes.

  1. Permit refused (planning authority Horsham, reference DC/24/0054)
  2. Permit applied for (planning authority Horsham, reference DC/24/0054)

How it compares

Kent Street, Cowfold - Battery Energy Storage System is the 171st-largest of 3,953 power plants in England and the 342nd-largest of 5,723 in the United Kingdom by capacity; its 57 MW is <0.1% of the 136,106 MW we hold for the United Kingdom. Ranks and totals cover the power plants in our data that report their capacity, not every one in existence. Power plants planned, permitted or under construction are ranked apart.

WithinRankTotalShare
England171st of 3,95385,679 MW<0.1%
United Kingdom342nd of 5,723136,106 MW<0.1%
All power plants in our data1,718th of 12,7051,210,931 MW<0.1%

Nearby

Within 50 km of this power plant: 43 grid connections (31 operating, 166 MW), 37 substations and 16 data centers, measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.

NameKindSizeStatusDistance
IBM HorshamData center——8.7 km
Five Oaks PrimarySubstation——15 km
Solar 3.905 MW grid connection at Five Oaks Farm PVGrid connection3.91 MWOperating15 km
Billingshurst PrimarySubstation——16 km
Digital Realty LGW15Data center——17 km
Digital Realty LGW16Data center——17 km
Malham Farm Solar & Storage grid connectionGrid connection20 MWPlanned19 km
Plaistow PrimarySubstation——23 km
Solar 4.75 MW grid connection at PlaistowGrid connection4.75 MWOperating24 km