Power plant · Cardiff, Wales, United Kingdom

Lamby Way Solar Farm

Lamby Way Solar Farm is a power plant in Cardiff, Wales, United Kingdom, with 8.9 MW of capacity, operated by Cardiff Council.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationCardiff (coordinates), WalesDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
AddressFormer Lamby Way landfill site, Lamby Way, Rumney, Cardiff, South Glamorgan, CF3 2HPDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
StatusOperating (operational)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Start year2020DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Permit date10 May 2019 (permit 19/00397/MJR, Town and Country Planning Act, issued by Cardiff)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Application date22 Feb 2019 (reference 19/00397/MJR, planning authority Cardiff)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Decision date10 May 2019 (granted, reference 19/00397/MJR, planning authority Cardiff)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
OperatorCardiff CouncilDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Capacity8.9 MWDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
TechnologySolar PhotovoltaicsDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Area16.9 ha (solar site area)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Coordinates51.4947, -3.1235DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026

Research on this power plant and its operator.Who owns it up to the parent company, its grid connection and planning status, and an introduction to the operator.

Request research

Latest events

Dated events about this power plant from official notices and registers, newest first. All recent changes.

  1. Commissioned
  2. Permit granted (planning authority Cardiff, reference 19/00397/MJR)
  3. Permit applied for (planning authority Cardiff, reference 19/00397/MJR)

How it compares

Lamby Way Solar Farm is the 163rd-largest of 424 power plants in Wales and the 2,096th-largest of 5,050 in the United Kingdom by capacity; its 8.9 MW is <0.1% of the 115,622 MW we hold for the United Kingdom. Ranks and totals cover the power plants in our data that report their capacity, not every one in existence. Power plants planned, permitted or under construction are ranked apart.

WithinRankTotalShare
Wales163rd of 4249,068 MW<0.1%
United Kingdom2,096th of 5,050115,622 MW<0.1%
All power plants in our data7,507th of 12,0321,190,447 MW<0.1%

Timeline

Dated facts about this power plant from its sources, oldest first.

  1. Started operating

Nearby

Within 50 km of this power plant: 9 data centers, 2 transmission lines and 1 AI supercomputer, measured from the coordinates in the facts above. The table shows the nearest 6, up to 3 per kind.

NameKindSizeStatusDistance
Microsoft Newport data centreData center——8.5 km
Vantage Data Centers data center, NewportData center——9.0 km
Centerprise International NewportData center——9.0 km
Hinkley Point C Connection Project Material ChangeTransmission line—Planned26 km
Hinkley Point C ConnectionTransmission line—Permitted30 km
University of Bristol Isambard-AIAI supercomputer5,448 H100eOperating45 km

Operator and place

Other power plants in Wales

All 616 power plants in Wales, United Kingdom

Data on this page