Power plant · Vale of Glamorgan, Wales, United Kingdom
East Aberthaw - Solar farm
East Aberthaw - Solar farm is a permitted power plant in Vale of Glamorgan, Wales, United Kingdom, with 35 MW of capacity, operated by Low Carbon UK Solar Investment Company Limited.
Facts
Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.
| Fact | Value | Source |
|---|---|---|
| Location | Vale of Glamorgan (coordinates), Wales | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Address | Fonmon, Barry, CF62 3BL | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Status | Permitted (planning permission granted) | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Permit date | 20 Dec 2024 (permit CAS-01391-M3G6Q9, Welsh Government development of national significance, issued by Welsh Government (NSIP)) | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Application date | 6 Nov 2023 (reference CAS-01391-M3G6Q9, planning authority Welsh Government (NSIP)) | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Decision date | 20 Dec 2024 (granted, reference CAS-01391-M3G6Q9, planning authority Welsh Government (NSIP)) | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Operator | Low Carbon UK Solar Investment Company Limited | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Capacity | 35 MW | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Technology | Solar Photovoltaics | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Area | 40.5 ha (solar site area) | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Coordinates | 51.3985, -3.3604 | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
Know more about this power plant, or want an introduction to its operator? Ask us.
How it compares
East Aberthaw - Solar farm is the 70th-largest of 177 power plants planned, permitted or under construction in Wales and the 1,489th-largest of 3,222 in the United Kingdom by capacity; its 35 MW is <0.1% of the 300,661 MW of power plants planned, permitted or under construction we hold for the United Kingdom. It is not built yet, so it is ranked among the power plants planned, permitted or under construction in our data, apart from the ones running today. Ranks and totals cover the ones that report their capacity.
| Within | Rank | Total | Share |
|---|---|---|---|
| Wales | 70th of 177 | 16,801 MW | 0.21% |
| United Kingdom | 1,489th of 3,222 | 300,661 MW | <0.1% |
| All power plants planned, permitted or under construction in our data | 2,772nd of 6,455 | 664,240 MW | <0.1% |
Nearby
Within 50 km of this power plant: 300 grid connections, 8 data centers and 2 transmission lines, measured from the coordinates in the facts above. The table shows the nearest 8, up to 3 per kind.
| Name | Kind | Size | Status | Distance |
|---|---|---|---|---|
| Fonmon Solar Farm grid connection | Grid connection | — | — | 0.6 km |
| Barry Rhoose grid connection | Grid connection | — | — | 1.4 km |
| Oaklands Solar Farm BESS grid connection | Grid connection | — | — | 2.2 km |
| CGI Datacenter | Data center | — | — | 18 km |
| Centerprise International (Distribution) | Data center | — | — | 27 km |
| Microsoft Newport data centre | Data center | — | — | 28 km |
| Hinkley Point C Connection Project Material Change | Transmission line | — | Planned | 37 km |
| Hinkley Point C Connection | Transmission line | — | Permitted | 41 km |
Operator and place
More from Low Carbon UK Solar Investment Company Limited
- Bluebell Wood Solar Farm & Battery Storage50 MW · permitted
- Callie's Solar Farm49.9 MW · permitted
- Fernbrook - Solar farm & Battery storage49.9 MW · permitted
- Canewdon Road, Canewdon - Solar Photovoltaic Farm49.9 MW · permitted
- Jafa, Great Dunham - Solar Photovoltaic Farm & Battery Storage49.9 MW · permitted
- Bluebell Wood Solar Farm & Battery Storage49.9 MW · permitted
- Elms Farm - Hinckley Solar Farm & Battery Storage49.9 MW · permitted
- Perham Down - Meadow Solar Farm & Battery Storage49.9 MW · permitted
Other power plants in Wales
- Dinorwig1,728 MW
- Gwynt y Mor576 MW
- Ffestiniog360 MW
- Port Talbot Renewable Energy Plant350 MW
- Anglesey Biomass Power Station299 MW
- Tidal Lagoon Swansea Bay240 MW
- Pen Y Cymoedd228 MW
- Carnedd Wen Wind Farm150 MW
Data on this page
- DESNZ Renewable Energy Planning Database (REPD). DESNZ Renewable Energy Planning Database (REPD), Open Government Licence v3.0.
- Source: U.S. Energy Information Administration (Sep 2026). EIA-860 / 860M / 923, Public domain.
- Bundesnetzagentur, Marktstammdatenregister. Marktstammdatenregister, DL-DE-BY-2.0.
- NGED Connected Data portal. NGED Connected Data portal, Terms not verified.
- © OpenStreetMap contributors. OpenStreetMap data centers, ODbL 1.0.
- Planning Inspectorate: National Infrastructure Projects. Planning Inspectorate: National Infrastructure Projects, Open Government Licence v3.0.
- RVO SDE(+)(+) projecten in beheer and SDE viewer. RVO SDE(+)(+) projecten in beheer and SDE viewer, Free reuse, no attribution required.