Power plant · Runnymede, England, United Kingdom

Trumps Farm (AD)

Trumps Farm (AD) is a power plant in Runnymede, England, United Kingdom, with 2.4 MW of capacity, operated by Severn Trent.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationRunnymede (coordinates), EnglandDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
AddressLong Cross, Chertsey, KT16 0EFDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
StatusOperating (operational)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Start year2014DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Permit date12 May 2011 (permit RU.10/0872, Town and Country Planning Act, issued by Runnymede)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Application date15 Sept 2010 (reference RU.10/0872, planning authority Runnymede)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Decision date12 May 2011 (granted, reference RU.10/0872, planning authority Runnymede)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
OperatorSevern Trent (Severn Trent (formerly Agrivert))DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Capacity2.4 MWDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
TechnologyAnaerobic DigestionDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Coordinates51.3823, -0.5691DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026

Research on this power plant and its operator.Who owns it up to the parent company, its grid connection and planning status, and an introduction to the operator.

Request research

Latest events

Dated events about this power plant from official notices and registers, newest first. All recent changes.

  1. Commissioned
  2. Permit granted (planning authority Runnymede, reference RU.10/0872)
  3. Permit applied for (planning authority Runnymede, reference RU.10/0872)

How it compares

Trumps Farm (AD) is the 2,708th-largest of 3,430 power plants in England and the 4,001st-largest of 5,050 in the United Kingdom by capacity; its 2.4 MW is <0.1% of the 115,622 MW we hold for the United Kingdom. Ranks and totals cover the power plants in our data that report their capacity, not every one in existence. Power plants planned, permitted or under construction are ranked apart.

WithinRankTotalShare
England2,708th of 3,43071,965 MW<0.1%
United Kingdom4,001st of 5,050115,622 MW<0.1%
All power plants in our data10,116th of 12,0321,190,447 MW<0.1%

Timeline

Dated facts about this power plant from its sources, oldest first.

  1. Started operating

Nearby

Within 50 km of this power plant: 199 substations, 149 data centers, 128 grid connections (69 operating, 737 MW) and 1 transmission line, measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.

NameKindSizeStatusDistance
MVEE PrimarySubstation——1.6 km
Ark Data Centres - Longcross ParkData center——1.8 km
Chobham PrimarySubstation——3.6 km
Waste 3.325 MW grid connection at CausewayGrid connection3.33 MWOperating5.0 km
Egham PrimarySubstation——5.8 km
Digital Realty LGW14Data center——6.6 km
Redcentric ByfleetData center——7.3 km
Ready - 50MW Battery grid connectionGrid connection50 MWPlanned8.2 km
Ready - 200MW Battery grid connectionGrid connection200 MWPlanned9.2 km

Operator and place

More from Severn Trent

Other power plants in England

All 5809 power plants in England, United Kingdom