Power plant · County Durham, England, United Kingdom

Thorn Lighting, Butchers Race - Solar Panels

Thorn Lighting, Butchers Race - Solar Panels is a permitted power plant in County Durham, England, United Kingdom, with 1.7 MW of capacity, operated by Colliers Building Consultancy Limited.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationCounty Durham (coordinates), EnglandDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
AddressThorn Lighting, Butchers Race, Green Lane Industrial Estate, Spennymoor, DL16 6PGDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
StatusPermitted (planning permission granted)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Permit date2 Aug 2024 (permit DM/24/01556/PN56, Town and Country Planning Act, issued by County Durham)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Application date11 Jun 2024 (ref. DM/24/01556/PN56, County Durham)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Decision date2 Aug 2024 (granted, ref. DM/24/01556/PN56, County Durham)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
OperatorColliers Building Consultancy LimitedDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Capacity1.7 MWDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
TechnologySolar PhotovoltaicsDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Coordinates54.7065, -1.5811DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026

Know more about this power plant, or want an introduction to its operator? Ask us.

How it compares

Thorn Lighting, Butchers Race - Solar Panels is the 1,900th-largest of 2,174 power plants planned, permitted or under construction in England and the 2,883rd-largest of 3,222 in the United Kingdom by capacity; its 1.7 MW is <0.1% of the 300,661 MW of power plants planned, permitted or under construction we hold for the United Kingdom. It is not built yet, so it is ranked among the power plants planned, permitted or under construction in our data, apart from the ones running today. Ranks and totals cover the ones that report their capacity.

WithinRankTotalShare
England1,900th of 2,174186,088 MW<0.1%
United Kingdom2,883rd of 3,222300,661 MW<0.1%
All power plants planned, permitted or under construction in our data6,091st of 6,455664,240 MW<0.1%

Nearby

Within 50 km of this power plant: 283 grid connections (142 operating, 1,377 MW) and 167 substations, measured from the coordinates in the facts above. The table shows the nearest 6, up to 3 per kind.

NameKindSizeStatusDistance
Low SpennymoorSubstation——1.2 km
Spennymoor 66/20kVSubstation——1.6 km
Spennymoor GSPSubstation——1.6 km
Solar 1.7 MW grid connection at Spennymoor 66/20kVGrid connection1.7 MWPlanned1.8 km
Solar 46.55 MW grid connection at Hett Moor Solar DirectGrid connection46.6 MWPlanned2.1 km
Battery storage 100 MW grid connection at The Tavern BESS DirectGrid connection100 MWPlanned2.4 km

Operator and place

Other power plants in England

All 5809 power plants in England, United Kingdom

Data on this page