Power plant · Arun, England, United Kingdom
Rookery Farm
Rookery Farm is a power plant in Arun, England, United Kingdom, with 3.8 MW of capacity, operated by Green Switch Solutions.
Facts
Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.
| Fact | Value | Source |
|---|---|---|
| Location | Arun (coordinates), England | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Address | Land between Bilsham and Flansham North of A259 Flansham, PO22 8NN | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Status | Operating (operational) | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Start year | 2015 | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Permit date | 29 May 2014 (permit Y/14/14/, Town and Country Planning Act, issued by Arun) | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Application date | 7 Mar 2014 (reference Y/14/14/, planning authority Arun) | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Decision date | 29 May 2014 (granted, reference Y/14/14/, planning authority Arun) | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Operator | Green Switch Solutions | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Capacity | 3.8 MW | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Technology | Solar Photovoltaics | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Area | 8.1 ha (solar site area) | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Coordinates | 50.8064, -0.6205 | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
Research on this power plant and its operator.Who owns it up to the parent company, its grid connection and planning status, and an introduction to the operator.
Request researchLatest events
Dated events about this power plant from official notices and registers, newest first. All recent changes.
- Commissioned
- Permit granted (planning authority Arun, reference Y/14/14/)
- Permit applied for (planning authority Arun, reference Y/14/14/)
How it compares
Rookery Farm is the 2,440th-largest of 3,430 power plants in England and the 3,623rd-largest of 5,050 in the United Kingdom by capacity; its 3.8 MW is <0.1% of the 115,622 MW we hold for the United Kingdom. Ranks and totals cover the power plants in our data that report their capacity, not every one in existence. Power plants planned, permitted or under construction are ranked apart.
| Within | Rank | Total | Share |
|---|---|---|---|
| England | 2,440th of 3,430 | 71,965 MW | <0.1% |
| United Kingdom | 3,623rd of 5,050 | 115,622 MW | <0.1% |
| All power plants in our data | 9,447th of 12,032 | 1,190,447 MW | <0.1% |
Timeline
Dated facts about this power plant from its sources, oldest first.
- Started operating
Nearby
Within 50 km of this power plant: 102 grid connections (60 operating, 554 MW), 83 substations, 11 data centers and 1 transmission line, measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.
| Name | Kind | Size | Status | Distance |
|---|---|---|---|---|
| Bilsham Primary | Substation | — | — | 0.1 km |
| Solar 10 MW grid connection at Bilsham | Grid connection | 10 MW | Operating | 0.4 km |
| Solar 10 MW grid connection at Bilsham | Grid connection | 10 MW | Operating | 0.4 km |
| Solar 3 MW grid connection at Bilsham | Grid connection | 3 MW | Operating | 1.2 km |
| South Bersted Primary | Substation | — | — | 3.4 km |
| Argyle Road Primary | Substation | — | — | 4.8 km |
| SSE data center, Havant | Data center | — | — | 26 km |
| IBM Horsham | Data center | — | — | 30 km |
| Aquind Interconnector | Transmission line | — | Planned | 32 km |
Operator and place
More from Green Switch Solutions
- Partridge Hill Solar Farm33 MW · permitted
- Wanes Blades Road Solar Farm16 MW
- Clay Tye Farm15.9 MW
- Wharrels Hill14.6 MW
- Hurst Hall13.3 MW
- Grange Farm (Lincolnshire)12.7 MW
- Land at Rectory Farm8.9 MW
- GDL Wymeswold Solar Farm/land off the A60066.1 MW
Other power plants in England
- Walpole Flexible Generation Project2,000 MW
- Outer Dowsing Offshore Wind Farm1,500 MW
- Hornsea 2 - Optimus and Breesea1,320 MW
- Hornsea 1 - Heron & Njord1,218 MW
- Atlantic Array One - Bristol Channel Zone1,200 MW
- Five Estuaries - Wind Farm1,080 MW
- Rugeley Power Plant Conversion1,000 MW
- Teesworks Battery Storage Project1,000 MW
Data on this page
- Contains public sector information licensed under the Open Government Licence v3.0. DESNZ Renewable Energy Planning Database (REPD), Open Government Licence v3.0.
- Source: U.S. Energy Information Administration (Sep 2026). EIA-860 / 860M / 923, Public domain.
- JRC Open Power Plants Database (JRC-PPDB-OPEN), European Commission, Joint Research Centre. JRC Open Power Plants Database (JRC-PPDB-OPEN), CC BY 4.0.
- Bundesnetzagentur, Marktstammdatenregister. Marktstammdatenregister, DL-DE-BY-2.0.
- Dutch power station owners' and operators' pages. Dutch power station owners' and operators' pages, Facts only, each linked to its page.
- © OpenStreetMap contributors. OpenStreetMap data centers, ODbL 1.0.
- Contains public sector information licensed under the Open Government Licence v3.0. Planning Inspectorate: National Infrastructure Projects, Open Government Licence v3.0.
- RVO SDE(+)(+) projecten in beheer and SDE viewer. RVO SDE(+)(+) projecten in beheer and SDE viewer, Free reuse, no attribution required.
- SSEN Distribution. SSEN Distribution data portal, CC BY 4.0.