Grid connection · England, United Kingdom

Solar 3 MW grid connection at Bilsham

Solar 3 MW grid connection at Bilsham is a grid connection in England, United Kingdom, with 3 MW of capacity, held by Solein Rookery Ltd.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
Name in the sourceSolar 3 MW grid connection at BILSHAMSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
LocationEngland (connects at Bilsham)SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
StatusOperating (connected)SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
HolderSolein Rookery LtdSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Attached toBilsham Primary (via a primary substation)SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Capacity3 MWSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
TechnologySolarSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Grid operatorSouthern Electric Power Distribution plcSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Connection date29 Mar 2015SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Voltage11 kVSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Coordinates50.8028, -0.6360SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026

Know more about this grid connection, or want an introduction to its holder? Ask us.

How it compares

Solar 3 MW grid connection at Bilsham is the 1,995th-largest of 2,533 grid connections in England and the 3,064th-largest of 3,903 in the United Kingdom by capacity; its 3 MW is <0.1% of the 446,745 MW we hold for the United Kingdom. Ranks and totals cover the grid connections in our data that report their capacity, not every one in existence.

WithinRankTotalShare
England1,995th of 2,533319,370 MW<0.1%
United Kingdom3,064th of 3,903446,745 MW<0.1%
All grid connections in our data6,749th of 7,6161,281,251 MW<0.1%

Nearby

Within 50 km of this grid connection: 154 power plants (70 operating, 865 MW), 87 substations and 1 transmission line, measured from the coordinates in the facts above. The table shows the nearest 7, up to 3 per kind.

NameKindSizeStatusDistance
Rookery FarmPower plant3.8 MWOperating1.2 km
Bilsham PrimarySubstation——1.2 km
Bilsham FarmPower plant14.5 MWOperating1.3 km
South Bersted PrimarySubstation——2.2 km
Land at BarnhamPower plant1 MWOperating2.4 km
Argyle Road PrimarySubstation——3.7 km
Aquind InterconnectorTransmission line—Planned31 km

Holder, grid operator and place

Other grid connections in England

All 3831 grid connections in England, United Kingdom