Power plant · Ashford, England, United Kingdom

Partridge Farm

Partridge Farm is a power plant in Ashford, England, United Kingdom, with 10.6 MW of capacity, operated by Eco Energy World.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationAshford (coordinates), EnglandDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
AddressLand south of National Grid Converter Station, Church Lane, Aldington, KentDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
StatusOperating (operational)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Start year2016DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Permit date6 Oct 2015 (permit 14/00398/AS, Town and Country Planning Act, issued by Ashford)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Application date28 Apr 2014 (reference 14/00398/AS, planning authority Ashford)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Decision date6 Oct 2015 (appeal granted, reference 14/00398/AS, planning authority Ashford)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Decision date22 Jul 2014 (refused, reference 14/00398/AS, planning authority Ashford)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Decision date6 Oct 2015 (granted, reference 14/00398/AS, planning authority Ashford)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
OperatorEco Energy WorldDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Capacity10.6 MWDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
TechnologySolar PhotovoltaicsDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Area25.3 ha (solar site area)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Coordinates51.1024, 0.9799DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026

Research on this power plant and its operator.Who owns it up to the parent company, its grid connection and planning status, and an introduction to the operator.

Request research

How it compares

Partridge Farm is the 1,067th-largest of 3,430 power plants in England and the 1,798th-largest of 5,050 in the United Kingdom by capacity; its 10.6 MW is <0.1% of the 115,642 MW we hold for the United Kingdom. Ranks and totals cover the power plants in our data that report their capacity, not every one in existence. Power plants planned, permitted or under construction are ranked apart.

WithinRankTotalShare
England1,067th of 3,43071,985 MW<0.1%
United Kingdom1,798th of 5,050115,642 MW<0.1%
All power plants in our data6,836th of 12,0081,173,302 MW<0.1%

Timeline

Dated facts about this power plant from its sources, oldest first.

  1. Permit issued (Town and Country Planning Act), no. 14/00398/AS
  2. Started operating

Nearby

Within 50 km of this power plant: 4 data centers and 1 transmission line, measured from the coordinates in the facts above. The table shows the nearest 4, up to 3 per kind.

NameKindSizeStatusDistance
The Bunker - South East Data CentreData center——29 km
Sota DatacentreData center——29 km
Richborough Connection ProjectTransmission line—Permitted30 km
CustodianDC MaidstoneData center——36 km

Operator and place

More from Eco Energy World

Other power plants in England

All 5809 power plants in England, United Kingdom

Data on this page