Junction House is a cancelled power plant in County Durham, England, United Kingdom, with 2.3 MW of capacity, operated by British Telecom.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationCounty Durham (coordinates), EnglandDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
AddressLand North of Pesspool Lane, Easington VillageDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
StatusCancelled (planning permission refused)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Onshore or offshoreOnshoreDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Application date9 Feb 2011 (reference PL/5/2010/0473, planning authority County Durham)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Decision date4 Oct 2011 (refused, reference PL/5/2010/0473, planning authority County Durham)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
OperatorBritish TelecomDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Capacity2.3 MWDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Units1 units (2.3 MW per unit)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
TechnologyWind OnshoreDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Coordinates54.7866, -1.3796DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026

Research on this power plant and its operator.Who owns it up to the parent company, its grid connection and planning status, and an introduction to the operator.

Request research

Latest events

Dated events about this power plant from official notices and registers, newest first. All recent changes.

  1. Permit refused (planning authority County Durham, reference PL/5/2010/0473)
  2. Permit applied for (planning authority County Durham, reference PL/5/2010/0473)

How it compares

Junction House is the 2,731st-largest of 3,430 power plants in England and the 4,056th-largest of 5,050 in the United Kingdom by capacity; its 2.3 MW is <0.1% of the 115,622 MW we hold for the United Kingdom. Ranks and totals cover the power plants in our data that report their capacity, not every one in existence. Power plants planned, permitted or under construction are ranked apart.

WithinRankTotalShare
England2,731st of 3,43071,965 MW<0.1%
United Kingdom4,056th of 5,050115,622 MW<0.1%
All power plants in our data10,205th of 12,0321,190,447 MW<0.1%

Nearby

Within 50 km of this power plant: 279 grid connections (140 operating, 1,776 MW), 164 substations and 5 data centers, measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.

NameKindSizeStatusDistance
Battery storage and Solar 25.2 MW grid connection at West Moor FarmGrid connection25.2 MWPlanned1.4 km
Battery storage 100 MW grid connection at Hawthorn Coke WorksGrid connection100 MWPlanned2.0 km
Battery storage 101.3 MW grid connection at Woodland BESSGrid connection101 MWPlanned2.0 km
Peterlee IndustrialSubstation——2.0 km
Hawthorn PitSubstation——2.5 km
Hawthorn Pit GridSubstation——2.6 km
DXC Wynyard Data CenterData center——18 km
Lumen Technologies data center, MiddlesbroughData center——25 km
Pulsant data center, EnglandData center——26 km

Operator and place

More from British Telecom

Other power plants in England

All 5809 power plants in England, United Kingdom

Data on this page