Power plant · North Kesteven, England, United Kingdom

Green Man Road, Navenby - Battery Storage

Green Man Road, Navenby - Battery Storage is a planned power plant in North Kesteven, England, United Kingdom, with 400 MW of capacity, operated by Windel Energy and Canadian solar.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationNorth Kesteven (coordinates), EnglandDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
AddressN/O Green Man Road, Navenby, Lincoln, LN5 0JYDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
StatusPlanned (planning application submitted)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Application date9 May 2025 (reference 25/0491/FUL, planning authority North Kesteven)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
OperatorWindel Energy (Windel Energy / Canadian Solar)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
OperatorCanadian solar (Windel Energy / Canadian Solar)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Capacity400 MWDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
TechnologyBattery (stand-alone storage)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Coordinates53.1113, -0.5181DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026

Research on this power plant and its operator.Who owns it up to the parent company, its grid connection and planning status, and an introduction to the operator.

Request research

Latest events

Dated events about this power plant from official notices and registers, newest first. All recent changes.

  1. Permit applied for (planning authority North Kesteven, reference 25/0491/FUL)

How it compares

Green Man Road, Navenby - Battery Storage is the 103rd-largest of 2,174 power plants planned, permitted or under construction in England and the 157th-largest of 3,222 in the United Kingdom by capacity; its 400 MW is 0.13% of the 300,461 MW of power plants planned, permitted or under construction we hold for the United Kingdom. It is not built yet, so it is ranked among the power plants planned, permitted or under construction in our data, apart from the ones running today. Ranks and totals cover the ones that report their capacity.

WithinRankTotalShare
England103rd of 2,174185,888 MW0.22%
United Kingdom157th of 3,222300,461 MW0.13%
All power plants planned, permitted or under construction in our data351st of 6,455664,040 MW<0.1%

Nearby

Within 50 km of this power plant: 29 grid connections (16 operating, 211 MW), 19 substations, 5 transmission lines and 3 data centers, measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.

NameKindSizeStatusDistance
Digital Space DC - NewarkData center——19 km
Hall Water Treatment Works grid connectionGrid connection1.6 MWOperating22 km
Newton on Trent Water Works grid connectionGrid connection3.1 MWOperating23 km
StowSubstation——26 km
Stow Park Road grid connectionGrid connection1.19 MWOperating26 km
Triton Knoll Electrical SystemTransmission line—Permitted28 km
NormanbySubstation——30 km
HarpswellSubstation——33 km
Eastern Green Link 3 and Eastern Green Link 4Transmission line—Planned33 km

Operators and place

More from Windel Energy

Other power plants in England

All 5809 power plants in England, United Kingdom

Data on this page