Power plant · Rochford, England, United Kingdom
Fairlawns Farm, Chelmsford Road - Battery Energy Storage
Fairlawns Farm, Chelmsford Road - Battery Energy Storage is a permitted power plant in Rochford, England, United Kingdom, with 480 MW of capacity, operated by Gresham House Devco Pipeline.
Facts
Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.
| Fact | Value | Source |
|---|---|---|
| Location | Rochford (coordinates), England | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Address | Fairlawns Farm, Chelmsford Road, Rayleigh, SS6 7EW | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Status | Permitted (planning permission granted) | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Permit date | 17 Jul 2025 (permit 24/00455/FUL, Town and Country Planning Act, issued by Rochford) | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Application date | 31 Jul 2024 (reference 24/00455/FUL, planning authority Rochford) | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Decision date | 17 Jul 2025 (granted, reference 24/00455/FUL, planning authority Rochford) | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Operator | Gresham House Devco Pipeline | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Capacity | 480 MW | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Technology | Battery (stand-alone storage) | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Coordinates | 51.5875, 0.6106 | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
Research on this power plant and its operator.Who owns it up to the parent company, its grid connection and planning status, and an introduction to the operator.
Request researchLatest events
Dated events about this power plant from official notices and registers, newest first. All recent changes.
- Permit granted (planning authority Rochford, reference 24/00455/FUL)
- Permit applied for (planning authority Rochford, reference 24/00455/FUL)
How it compares
Fairlawns Farm, Chelmsford Road - Battery Energy Storage is the 93rd-largest of 2,174 power plants planned, permitted or under construction in England and the 143rd-largest of 3,222 in the United Kingdom by capacity; its 480 MW is 0.16% of the 300,461 MW of power plants planned, permitted or under construction we hold for the United Kingdom. It is not built yet, so it is ranked among the power plants planned, permitted or under construction in our data, apart from the ones running today. Ranks and totals cover the ones that report their capacity.
| Within | Rank | Total | Share |
|---|---|---|---|
| England | 93rd of 2,174 | 185,888 MW | 0.26% |
| United Kingdom | 143rd of 3,222 | 300,461 MW | 0.16% |
| All power plants planned, permitted or under construction in our data | 305th of 6,455 | 664,040 MW | <0.1% |
Nearby
Within 50 km of this power plant: 48 data centers (1 operating, 88 MW), 2 grid connections (1 operating, 6.94 MW), 2 transmission lines and 1 AI supercomputer, measured from the coordinates in the facts above. The table shows the nearest 8, up to 3 per kind.
| Name | Kind | Size | Status | Distance |
|---|---|---|---|---|
| CityFibre Cabinets | Data center | — | — | 3.0 km |
| Imperium 315 | Data center | — | — | 8.7 km |
| Fujitsu Data Centre | Data center | — | — | 26 km |
| Solar 6.935 MW grid connection at Maiden Newton | Grid connection | 6.94 MW | Operating | 39 km |
| NVIDIA Cambridge-1 | AI supercomputer | 202 H100e | Operating | 39 km |
| North London (Electricity Line) Reinforcement | Transmission line | — | Permitted | 45 km |
| Tertiary Study grid connection | Grid connection | 57 MW | Planned | 49 km |
| Bramford to Twinstead | Transmission line | — | Permitted | 50 km |
Operator and place
More from Gresham House Devco Pipeline
- Gretna Green Battery Storage456 MW · permitted
- Kincardine Battery Storage342 MW · permitted
- Mossmorran Battery Storage300 MW · permitted
- Midland Quarry Products, Smith Road - Battery Storage10 MW · permitted
Other power plants in England
- Walpole Flexible Generation Project2,000 MW
- Outer Dowsing Offshore Wind Farm1,500 MW
- Hornsea 2 - Optimus and Breesea1,320 MW
- Hornsea 1 - Heron & Njord1,218 MW
- Atlantic Array One - Bristol Channel Zone1,200 MW
- Five Estuaries - Wind Farm1,080 MW
- Rugeley Power Plant Conversion1,000 MW
- Teesworks Battery Storage Project1,000 MW
Data on this page
- Contains public sector information licensed under the Open Government Licence v3.0. DESNZ Renewable Energy Planning Database (REPD), Open Government Licence v3.0.
- Source: U.S. Energy Information Administration (Sep 2026). EIA-860 / 860M / 923, Public domain.
- Epoch AI. Epoch AI supercomputers, CC BY 4.0.
- Bundesnetzagentur, Marktstammdatenregister. Marktstammdatenregister, DL-DE-BY-2.0.
- © OpenStreetMap contributors. OpenStreetMap data centers, ODbL 1.0.
- Contains public sector information licensed under the Open Government Licence v3.0. Planning Inspectorate: National Infrastructure Projects, Open Government Licence v3.0.
- RVO SDE(+)(+) projecten in beheer and SDE viewer. RVO SDE(+)(+) projecten in beheer and SDE viewer, Free reuse, no attribution required.
- SSEN Distribution. SSEN Distribution data portal, CC BY 4.0.