Power plant · Sandwell, England, United Kingdom

Midland Quarry Products, Smith Road - Battery Storage

Midland Quarry Products, Smith Road - Battery Storage is a permitted power plant in Sandwell, England, United Kingdom, with 10 MW of capacity, operated by Gresham House Devco Pipeline.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationSandwell (coordinates), EnglandDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
AddressAdjacent Midland Quarry Products Smith Road, WS10 0PBDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
StatusPermitted (planning permission granted)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Permit date31 Jan 2025 (permit DC/24/69271, Town and Country Planning Act, issued by Sandwell)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Application date2 May 2024 (reference DC/24/69271, planning authority Sandwell)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Decision date31 Jan 2025 (granted, reference DC/24/69271, planning authority Sandwell)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
OperatorGresham House Devco PipelineDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Capacity10 MWDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
TechnologyBattery (stand-alone storage)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Coordinates52.5466, -2.0217DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026

Research on this power plant and its operator.Who owns it up to the parent company, its grid connection and planning status, and an introduction to the operator.

Request research

Latest events

Dated events about this power plant from official notices and registers, newest first. All recent changes.

  1. Permit granted (planning authority Sandwell, reference DC/24/69271)
  2. Permit applied for (planning authority Sandwell, reference DC/24/69271)

How it compares

Midland Quarry Products, Smith Road - Battery Storage is the 1,441st-largest of 2,174 power plants planned, permitted or under construction in England and the 2,237th-largest of 3,222 in the United Kingdom by capacity; its 10 MW is <0.1% of the 300,461 MW of power plants planned, permitted or under construction we hold for the United Kingdom. It is not built yet, so it is ranked among the power plants planned, permitted or under construction in our data, apart from the ones running today. Ranks and totals cover the ones that report their capacity.

WithinRankTotalShare
England1,441st of 2,174185,888 MW<0.1%
United Kingdom2,237th of 3,222300,461 MW<0.1%
All power plants planned, permitted or under construction in our data5,307th of 6,455664,040 MW<0.1%

Nearby

Within 50 km of this power plant: 5 data centers, measured from the coordinates in the facts above. The table shows the nearest 3.

NameKindSizeStatusDistance
Hutchison 3GData center——0.6 km
EE Data CentreData center——1.9 km
Evoque Data Center SolutionsData center——28 km

Operator and place

More from Gresham House Devco Pipeline

Other power plants in England

All 5809 power plants in England, United Kingdom

Data on this page