Power plant · County Durham, England, United Kingdom

Edge Lane, Maiden Law - Solar Farm & Battery Storage

Edge Lane, Maiden Law - Solar Farm & Battery Storage is a permitted power plant in County Durham, England, United Kingdom, with 45 MW of capacity, operated by Lightsource BP.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationCounty Durham (coordinates), EnglandDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
AddressEast Of Edge Lane Maiden Law, DH7 0RYDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
StatusPermitted (appeal granted)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Permit date22 Apr 2026 (permit DM/22/01769/FPA, Town and Country Planning Act, issued by County Durham)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Application date30 Jun 2022 (reference DM/22/01769/FPA, planning authority County Durham)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Decision date10 Mar 2025 (refused, reference DM/22/01769/FPA, planning authority County Durham)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Decision date22 Apr 2026 (appeal granted, reference DM/22/01769/FPA, planning authority County Durham)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Decision date22 Apr 2026 (granted, reference DM/22/01769/FPA, planning authority County Durham)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
OperatorLightsource BPDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Capacity45 MWDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
TechnologyBattery (co-located with re)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Coordinates54.8361, -1.7211DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026

Research on this power plant and its operator.Who owns it up to the parent company, its grid connection and planning status, and an introduction to the operator.

Request research

Latest events

Dated events about this power plant from official notices and registers, newest first. All recent changes.

  1. Permit granted (appeal granted, planning authority County Durham, reference DM/22/01769/FPA)
  2. Permit granted (planning authority County Durham, reference DM/22/01769/FPA)
  3. Permit refused (planning authority County Durham, reference DM/22/01769/FPA)
  4. Permit applied for (planning authority County Durham, reference DM/22/01769/FPA)

How it compares

Edge Lane, Maiden Law - Solar Farm & Battery Storage is the 811th-largest of 2,174 power plants planned, permitted or under construction in England and the 1,289th-largest of 3,222 in the United Kingdom by capacity; its 45 MW is <0.1% of the 300,461 MW of power plants planned, permitted or under construction we hold for the United Kingdom. It is not built yet, so it is ranked among the power plants planned, permitted or under construction in our data, apart from the ones running today. Ranks and totals cover the ones that report their capacity.

WithinRankTotalShare
England811th of 2,174185,888 MW<0.1%
United Kingdom1,289th of 3,222300,461 MW<0.1%
All power plants planned, permitted or under construction in our data2,422nd of 6,455664,040 MW<0.1%

Nearby

Within 50 km of this power plant: 279 grid connections (144 operating, 1,918 MW), 165 substations and 4 data centers, measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.

NameKindSizeStatusDistance
Solar 41.8 MW grid connection at Moor Leaze Solar DirectGrid connection41.8 MWPlanned0.7 km
Solar 4.15 MW grid connection at Annfield 66/20kVGrid connection4.15 MWOperating1.6 km
Battery storage 46.55 MW grid connection at Morrow Edge SolarGrid connection46.6 MWPlanned1.6 km
AnnfieldSubstation——1.7 km
Annfield 66/20kVSubstation——1.7 km
TanfieldSubstation——5.7 km
Stellium Newcastle CampusData center——24 km
DXC Wynyard Data CenterData center——35 km
Pulsant data center, EnglandData center——41 km

Operator and place

More from Lightsource BP

Other power plants in England

All 5809 power plants in England, United Kingdom

Data on this page