Power plant · Swale, England, United Kingdom

Cleve Hill Solar Park

Cleve Hill Solar Park is a permitted power plant in Swale, England, United Kingdom made up of 2 power plants with 523 MW of capacity between them, operated by Cleve Hill Solar Park Ltd.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationSwale (coordinates), England (South East)Planning Inspectorate: National Infrastructure Projects · record · Open Government Licence v3.0 · checked 24 Oct 2026
AddressLand approximately 2 km northeast of Faversham and 5 km west of Whitstable on the North Kent Coast.Planning Inspectorate: National Infrastructure Projects · record · Open Government Licence v3.0 · checked 24 Oct 2026
StatusPermitted (post-decision, granted)Planning Inspectorate: National Infrastructure Projects · record · Open Government Licence v3.0 · checked 24 Oct 2026
Permit date28 May 2020 (permit EN010085, Planning Act 2008 development consent, issued by Secretary of State)Planning Inspectorate: National Infrastructure Projects · record · Open Government Licence v3.0 · checked 24 Oct 2026
Application date16 Nov 2018 (reference EN010085, planning authority The Planning Inspectorate)Planning Inspectorate: National Infrastructure Projects · record · Open Government Licence v3.0 · checked 24 Oct 2026
Decision date28 May 2020 (granted, reference EN010085, planning authority The Planning Inspectorate)Planning Inspectorate: National Infrastructure Projects · record · Open Government Licence v3.0 · checked 24 Oct 2026
OperatorCleve Hill Solar Park Ltd (applicant)Planning Inspectorate: National Infrastructure Projects · record · Open Government Licence v3.0 · checked 24 Oct 2026
TechnologySolar PhotovoltaicsPlanning Inspectorate: National Infrastructure Projects · record · Open Government Licence v3.0 · checked 24 Oct 2026
Area406 ha (application boundary)planning.data.gov.uk · record · Open Government Licence v3.0 · checked 24 Oct 2026
Coordinates51.3385, 0.9243Planning Inspectorate: National Infrastructure Projects · record · Open Government Licence v3.0 · checked 24 Oct 2026

Research on this power plant and its operator.Who owns it up to the parent company, its grid connection and planning status, and an introduction to the operator.

Request research

Latest events

Dated events about this power plant and the records linked to it from official notices and registers, newest first: the latest 8 of 10. All recent changes.

  1. Commissioned: Cleve Hill Solar Project
  2. Commissioned: Cleve Hill Solar Project
  3. Permit granted: Cleve Hill Solar Project (planning authority The Planning Inspectorate - National Infrastructure, reference EN010085)
  4. Permit refused: Cleve Hill Solar Project (planning authority The Planning Inspectorate - National Infrastructure, reference EN010085)
  5. Permit granted (planning authority The Planning Inspectorate, reference EN010085) · source
  6. Permit granted: Cleve Hill Solar Project (planning authority The Planning Inspectorate - National Infrastructure, reference EN010085)
  7. Permit refused: Cleve Hill Solar Project (planning authority The Planning Inspectorate - National Infrastructure, reference EN010085)
  8. Permit applied for (planning authority The Planning Inspectorate, reference EN010085) · source

How it compares by area

Cleve Hill Solar Park is the 94th-largest of 2,300 power plants in England and the 103rd-largest of 2,673 in the United Kingdom by area, with 406 ha. It reports no capacity, so it is ranked by area among the power plants in our data that report one, whatever their status. Areas of shared titles overlap, so they are not added up.

WithinRank
England94th of 2,300
United Kingdom103rd of 2,673
All power plants in our data124th of 2,695

Nearby

Within 50 km of this power plant: 8 data centers and 1 transmission line, measured from the coordinates in the facts above. The table shows the nearest 4, up to 3 per kind.

NameKindSizeStatusDistance
Sota DatacentreData center——14 km
Richborough Connection ProjectTransmission line—Permitted22 km
CustodianDC MaidstoneData center——27 km
The Bunker - South East Data CentreData center——27 km

Operator and place

How its power plants compare

The 2 power plants in this power plant, with their share of its 523 MW of capacity.

Power plantLocationOwnerStatusCapacityShare
Cleve Hill Solar ProjectSwale, England, United Kingdom—Operating373 MW71%
Cleve Hill Solar ProjectSwale, England, United Kingdom—Operating150 MW29%

Other power plants in England

All 5809 power plants in England, United Kingdom