Power plant · England, United Kingdom

Burbo Bank Extension (Burbo Bank 2)

Burbo Bank Extension (Burbo Bank 2) is a power plant in England, United Kingdom, with 258 MW of capacity, operated by Orsted and DONG Energy Burbo Extension Ltd.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationEnglandDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
LocationEngland (North West)Planning Inspectorate: National Infrastructure Projects · record · Open Government Licence v3.0 · checked 24 Oct 2026
AddressBurbo Flats, Liverpool Bay, approximately 6.4km (4.0 miles) from the Sefton coastline and 7.2km (4.5 miles) from North Wirral.DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
AddressLiverpool Bay NW of Wirral CoastPlanning Inspectorate: National Infrastructure Projects · record · Open Government Licence v3.0 · checked 24 Oct 2026
StatusOperating (operational)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
StatusPermitted (post-decision, granted)Planning Inspectorate: National Infrastructure Projects · record · Open Government Licence v3.0 · checked 24 Oct 2026
Start year2017DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Onshore or offshoreOffshoreDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Onshore or offshoreOffshorePlanning Inspectorate: National Infrastructure Projects · record · Open Government Licence v3.0 · checked 24 Oct 2026
Permit date10 Dec 2014 (permit EN010026, Planning Act 2008 development consent, issued by The Planning Inspectorate - National Infrastructure)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Permit date26 Sept 2014 (permit EN010026, Planning Act 2008 development consent, issued by Secretary of State)Planning Inspectorate: National Infrastructure Projects · record · Open Government Licence v3.0 · checked 24 Oct 2026
Application date22 Mar 2013 (reference EN010026, planning authority The Planning Inspectorate - National Infrastructure)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Application date22 Mar 2013 (reference EN010026, planning authority The Planning Inspectorate)Planning Inspectorate: National Infrastructure Projects · record · Open Government Licence v3.0 · checked 24 Oct 2026
Decision date10 Dec 2014 (granted, reference EN010026, planning authority The Planning Inspectorate - National Infrastructure)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Decision date26 Sept 2014 (granted, reference EN010026, planning authority The Planning Inspectorate)Planning Inspectorate: National Infrastructure Projects · record · Open Government Licence v3.0 · checked 24 Oct 2026
OperatorOrsted (Orsted (formerly Dong Energy))DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
OperatorDONG Energy Burbo Extension Ltd. (applicant)Planning Inspectorate: National Infrastructure Projects · record · Open Government Licence v3.0 · checked 24 Oct 2026
Capacity258 MWDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Capacity250 MW (description)Planning Inspectorate: National Infrastructure Projects · record · Open Government Licence v3.0 · checked 24 Oct 2026
Units32 units (8 MW per unit)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
TechnologyWind OffshoreDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
TechnologyWind OffshorePlanning Inspectorate: National Infrastructure Projects · record · Open Government Licence v3.0 · checked 24 Oct 2026
Area4,220 ha (application boundary)planning.data.gov.uk · record · Open Government Licence v3.0 · checked 24 Oct 2026
Coordinates53.4809, -3.2674DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026

Research on this power plant and its operator.Who owns it up to the parent company, its grid connection and planning status, and an introduction to the operator.

Request research

Also recorded as

2 sources record Burbo Bank Extension (Burbo Bank 2); this page joins their facts, each with its own source. Links to any of the records lead here. How records are matched.

Name in the sourceIdentifierSourceMatched on
Burbo Bank Extension (Burbo Bank 2)asset:repd:2539DESNZ Renewable Energy Planning Database (REPD)—
Burbo Bank Extension offshore wind farmasset:pins-nsip:en010026Planning Inspectorate: National Infrastructure ProjectsSame planning reference

How it compares

Burbo Bank Extension (Burbo Bank 2) is the 48th-largest of 3,430 power plants in England and the 67th-largest of 5,050 in the United Kingdom by capacity; its 258 MW is 0.22% of the 115,642 MW we hold for the United Kingdom. Ranks and totals cover the power plants in our data that report their capacity, not every one in existence. Power plants planned, permitted or under construction are ranked apart.

WithinRankTotalShare
England48th of 3,43071,985 MW0.36%
United Kingdom67th of 5,050115,642 MW0.22%
All power plants in our data1,013th of 12,0081,173,302 MW<0.1%

Timeline

Dated facts about this power plant from its sources, oldest first.

  1. Permit issued (Planning Act 2008 development consent), no. EN010026
  2. Permit issued (Planning Act 2008 development consent), no. EN010026
  3. Started operating

Nearby

Within 50 km of this power plant: 106 grid connections (61 operating, 502 MW), 82 substations, 6 data centers and 2 transmission lines, measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.

NameKindSizeStatusDistance
nLighten Edge Data Centre LiverpoolData center——25 km
ScarisbrickSubstation——26 km
Landsdale Nurseries grid connectionGrid connection6 MWOperating26 km
Bickerstaffe WTW grid connectionGrid connection1.25 MWOperating27 km
OrmskirkSubstation——27 km
Halsalls Lodge grid connectionGrid connection119 MWPlanned31 km
Washway Farm / Kirkby GSPSubstation——31 km
nLighten ChesterData center——34 km
Morgan and Morecambe Offshore Wind Farms Transmission AssetsTransmission line—Permitted35 km

Operators and place

More from Orsted

Other power plants in England

All 5809 power plants in England, United Kingdom

Data on this page