Power plant · England, United Kingdom
Hornsea 4
Hornsea 4 is a power plant in England, United Kingdom, with 2,400 MW of capacity, operated by Orsted and Orsted Hornsea Project Four Limited.
Facts
Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.
| Fact | Value | Source |
|---|---|---|
| Location | England | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Location | England (Yorkshire and the Humber) | Planning Inspectorate: National Infrastructure Projects · record · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Location | United Kingdom | NESO TEC Register · NESO Open Data Licence v1.0 · checked 24 Oct 2026 |
| Address | 69km offshore from Flamborough | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Address | Approximately 90km offshore, to the east of Hornsea | Planning Inspectorate: National Infrastructure Projects · record · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Status | Permitted (planning permission granted) | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Status | Permitted (post-decision, granted) | Planning Inspectorate: National Infrastructure Projects · record · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Onshore or offshore | Offshore | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Onshore or offshore | Offshore | Planning Inspectorate: National Infrastructure Projects · record · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Permit date | 12 Jul 2023 (permit EN010098, Planning Act 2008 development consent, issued by The Planning Inspectorate - National Infrastructure) | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Permit date | 12 Jul 2023 (permit EN010098, Planning Act 2008 development consent, issued by Secretary of State) | Planning Inspectorate: National Infrastructure Projects · record · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Application date | 29 Sept 2021 (reference EN010098, planning authority The Planning Inspectorate - National Infrastructure) | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Application date | 29 Sept 2021 (reference EN010098, planning authority The Planning Inspectorate) | Planning Inspectorate: National Infrastructure Projects · record · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Decision date | 12 Jul 2023 (granted, reference EN010098, planning authority The Planning Inspectorate - National Infrastructure) | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Decision date | 12 Jul 2023 (granted, reference EN010098, planning authority The Planning Inspectorate) | Planning Inspectorate: National Infrastructure Projects · record · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Operator | Orsted (Orsted (formerly Dong Energy)) | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Operator | Orsted Hornsea Project Four Limited (applicant) | Planning Inspectorate: National Infrastructure Projects · record · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Capacity | 2,400 MW | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Units | 180 units (14.4 MW per unit) | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Technology | Wind Offshore | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Technology | Wind Offshore | Planning Inspectorate: National Infrastructure Projects · record · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Area | 76,304 ha (application boundary) | planning.data.gov.uk · record · Open Government Licence v3.0 · checked 24 Oct 2026 |
| Coordinates | 53.6823, 1.4245 | DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026 |
Know more about this power plant, or want an introduction to its operator? Ask us.
Also recorded as
3 sources record Hornsea 4; this page joins their facts, each with its own source. Links to any of the records lead here. How records are matched.
| Name in the source | Identifier | Source | Matched on |
|---|---|---|---|
| Hornsea 4 | asset:repd:2473 | DESNZ Renewable Energy Planning Database (REPD) | — |
| Hornsea Project Four Offshore Wind Farm | asset:pins-nsip:en010098 | Planning Inspectorate: National Infrastructure Projects | Same name, technology and company |
| Hornsea Power Station 4 | asset:neso-tec:pro-000435 | NESO TEC Register | Same name, technology and company |
How it compares
Hornsea 4 is the 4th-largest of 2,174 power plants planned, permitted or under construction in England and the 8th-largest of 3,222 in the United Kingdom by capacity; its 2,400 MW is 0.8% of the 300,661 MW of power plants planned, permitted or under construction we hold for the United Kingdom. It is not built yet, so it is ranked among the power plants planned, permitted or under construction in our data, apart from the ones running today. Ranks and totals cover the ones that report their capacity.
| Within | Rank | Total | Share |
|---|---|---|---|
| England | 4th of 2,174 | 186,088 MW | 1.3% |
| United Kingdom | 8th of 3,222 | 300,661 MW | 0.8% |
| All power plants planned, permitted or under construction in our data | 15th of 6,455 | 664,240 MW | 0.36% |
Operators and place
Grid connections attached to this power plant
More from Orsted
- Hornsea 32,955 MW · under construction
- Hornsea 2 - Optimus and Breesea1,320 MW
- Hornsea 1 - Heron & Njord1,218 MW
- Walney 3659 MW
- Race Bank (Phase 1)290 MW
- Race Bank (Phase 2)284 MW
- Centrica (Lincs)270 MW
- Burbo Bank Extension (Burbo Bank 2)258 MW
Other power plants in England
- Walpole Flexible Generation Project2,000 MW
- Outer Dowsing Offshore Wind Farm1,500 MW
- Hornsea 2 - Optimus and Breesea1,320 MW
- Hornsea 1 - Heron & Njord1,218 MW
- Atlantic Array One - Bristol Channel Zone1,200 MW
- Five Estuaries - Wind Farm1,080 MW
- Rugeley Power Plant Conversion1,000 MW
- Teesworks Battery Storage Project1,000 MW
Data on this page
- DESNZ Renewable Energy Planning Database (REPD). DESNZ Renewable Energy Planning Database (REPD), Open Government Licence v3.0.
- Source: U.S. Energy Information Administration (Sep 2026). EIA-860 / 860M / 923, Public domain.
- Bundesnetzagentur, Marktstammdatenregister. Marktstammdatenregister, DL-DE-BY-2.0.
- Supported by National Energy SO Open Data. NESO TEC Register, NESO Open Data Licence v1.0.
- Planning Inspectorate: National Infrastructure Projects. Planning Inspectorate: National Infrastructure Projects, Open Government Licence v3.0.
- planning.data.gov.uk. planning.data.gov.uk, Open Government Licence v3.0.
- RVO SDE(+)(+) projecten in beheer and SDE viewer. RVO SDE(+)(+) projecten in beheer and SDE viewer, Free reuse, no attribution required.