Power plant · Boston, England, United Kingdom

Bicker Drove - Battery Energy Storage System

Bicker Drove - Battery Energy Storage System is a permitted power plant in Boston, England, United Kingdom, with 100 MW of capacity, operated by Net Zero Twenty Two Limited.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationBoston (coordinates), EnglandDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
AddressN/O Bicker Drove, Boston, PE20 3BQDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
StatusPermitted (planning permission granted)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Permit date5 Feb 2025 (permit B/24/0374, Town and Country Planning Act, issued by Boston)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Application date17 Sept 2024 (reference B/24/0374, planning authority Boston)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Decision date5 Feb 2025 (granted, reference B/24/0374, planning authority Boston)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
OperatorNet Zero Twenty Two LimitedDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Capacity100 MWDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
TechnologyBattery (stand-alone storage)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Coordinates52.9405, -0.2002DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026

Research on this power plant and its operator.Who owns it up to the parent company, its grid connection and planning status, and an introduction to the operator.

Request research

Latest events

Dated events about this power plant from official notices and registers, newest first. All recent changes.

  1. Permit granted (planning authority Boston, reference B/24/0374)
  2. Permit applied for (planning authority Boston, reference B/24/0374)

How it compares

Bicker Drove - Battery Energy Storage System is the 248th-largest of 2,174 power plants planned, permitted or under construction in England and the 426th-largest of 3,222 in the United Kingdom by capacity; its 100 MW is <0.1% of the 300,461 MW of power plants planned, permitted or under construction we hold for the United Kingdom. It is not built yet, so it is ranked among the power plants planned, permitted or under construction in our data, apart from the ones running today. Ranks and totals cover the ones that report their capacity.

WithinRankTotalShare
England248th of 2,174185,888 MW<0.1%
United Kingdom426th of 3,222300,461 MW<0.1%
All power plants planned, permitted or under construction in our data1,276th of 6,455664,040 MW<0.1%

Nearby

Within 50 km of this power plant: 4 transmission lines, 4 data centers, 2 substations and 1 grid connection (5 MW), measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.

NameKindSizeStatusDistance
Triton Knoll Electrical SystemTransmission line—Permitted1.7 km
Eastern Green Link 3 and Eastern Green Link 4Transmission line—Planned8.2 km
Digital Space DC - NewarkData center——42 km
Data center, England (OSM way 87850427)Data center——43 km
Positive ParkData center——43 km
Belmont CovertSubstation——44 km
Grimsby to WalpoleTransmission line—Planned45 km
Solar 5 MW grid connection at South RestonGrid connection5 MWOperating46 km
South RestonSubstation——47 km

Operator and place

Other power plants in England

All 5809 power plants in England, United Kingdom

Data on this page