Grid connection · England, United Kingdom
(ANM) Scolding Drove grid connection
(ANM) Scolding Drove grid connection is a planned grid connection in England, United Kingdom, with 50 MW of capacity, held by Cambridge Power Limited.
Facts
Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.
| Fact | Value | Source |
|---|---|---|
| Location | England (connects at Walpole) | UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026 |
| Status | Planned (accepted to connect) | UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026 |
| Holder | Cambridge Power Limited | UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026 |
| Capacity | 50 MW | UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026 |
| Technology | Solar | UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026 |
| Grid operator | Eastern Power Networks plc (UK Power Networks, East England licence area) | UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026 |
| Queue date | 4 Jul 2021 | UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026 |
| Voltage | 33 kV | UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026 |
| Coordinates | 52.6449, -0.0415 | UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026 |
Research on this grid connection and its holder.Who holds it up to the parent company, the project behind it and its connection date, and an introduction to the holder.
How it compares
(ANM) Scolding Drove grid connection is the 604th-largest of 3,539 grid connections in England and the 862nd-largest of 4,870 in the United Kingdom by capacity; its 50 MW is <0.1% of the 467,981 MW we hold for the United Kingdom. Ranks and totals cover the grid connections in our data that report their capacity, not every one in existence.
| Within | Rank | Total | Share |
|---|---|---|---|
| England | 604th of 3,539 | 341,715 MW | <0.1% |
| United Kingdom | 862nd of 4,870 | 467,981 MW | <0.1% |
| All grid connections in our data | 3,969th of 8,618 | 1,355,288 MW | <0.1% |
Nearby
Within 50 km of this grid connection: 339 power plants (125 operating, 3,945 MW), 71 substations, 7 data centers and 3 transmission lines, measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.
| Name | Kind | Size | Status | Distance |
|---|---|---|---|---|
| Nutsgrove Farm, Thorney - Battery Energy Storage | Power plant | 50 MW | Permitted | 0.2 km |
| Nutsgrove Farm, Thorney - Solar Array | Power plant | 49.9 MW | Permitted | 0.2 km |
| Nutsgrove Wind Farm | Power plant | 14.4 MW | Cancelled | 0.2 km |
| Guyhirn Primary 11kV | Substation | — | — | 8.5 km |
| Positive Park | Data center | — | — | 9.5 km |
| March Primary 11kV | Substation | — | — | 12 km |
| Whittlesey Primary 11kV | Substation | — | — | 12 km |
| Data center, England (OSM way 87850427) | Data center | — | — | 18 km |
| Kings Lynn B Connection Project | Transmission line | — | Permitted | 29 km |
Holder, grid operator and place
More from Cambridge Power Limited
- (ANM) High Road grid connection50 MW
- (ANM) Third Drove grid connection50 MW
- Battery storage 49.9 MW grid connection at Eaton Socon49.9 MW
- Bullen Lane - Battery Storage100 MW · under construction
- Redcote Lane, Armley - Battery Storage Facility60 MW
- Nutsgrove Farm, Thorney - Battery Energy Storage50 MW · permitted
- Greens Farm - Battery energy storage50 MW · permitted
- Nutsgrove Farm, Thorney - Solar Array49.9 MW · permitted
Other grid connections in England
- Bute Hydrogen Project 1 grid connection4,800 MW
- Drax BECCS grid connection3,906 MW
- Drax Power Station grid connection3,906 MW
- Bute Hydrogen Project 2 grid connection3,600 MW
- Bute Hydrogen Project 3 grid connection3,600 MW
- Bute Hydrogen Project 5 grid connection3,600 MW
- Bute Hydrogen Project 6 grid connection3,600 MW
- Hinkley Point C grid connection3,340 MW
Data on this page
- California ISO. CAISO queue report, CAISO Privacy and Terms of Use.
- Contains public sector information licensed under the Open Government Licence v3.0. DESNZ Renewable Energy Planning Database (REPD), Open Government Licence v3.0.
- SP Electricity North West, via Northern Powergrid Open Data. SP Electricity North West open data portal, CC BY 4.0.
- ERCOT GIS report. ERCOT GIS report, ERCOT Terms of Use.
- Supported by National Energy SO Open Data. NESO TEC Register, NESO Open Data Licence v1.0.
- Supported by Northern Powergrid Open Data. Northern Powergrid open data portal, Northern Powergrid Open Data Licence v1.0.
- NYISO interconnection queue. NYISO interconnection queue, Free reuse.
- © OpenStreetMap contributors. OpenStreetMap data centers, ODbL 1.0.
- Contains public sector information licensed under the Open Government Licence v3.0. Planning Inspectorate: National Infrastructure Projects, Open Government Licence v3.0.
- PJM New Services Queue. PJM New Services Queue, Free reuse.
- SP Energy Networks, via Northern Powergrid Open Data. SP Energy Networks open data portal, CC BY 4.0.
- SSEN Distribution. SSEN Distribution data portal, CC BY 4.0.
- UK Power Networks. UK Power Networks open data portal, CC BY 4.0.