Grid connection · England, United Kingdom

(ANM) East Of Guanockgate Road grid connection

(ANM) East Of Guanockgate Road grid connection is a planned grid connection in England, United Kingdom, with 78 MW of capacity, held by PACE Titan Energy Limited C/O External Services Limited.

Map: where (ANM) East Of Guanockgate Road grid connection lies
52.6871, 0.0786 on OpenStreetMap

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationEngland (connects at Walpole)UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
StatusPlanned (accepted to connect)UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
HolderPACE Titan Energy Limited C/O External Services LimitedUK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
Capacity78 MWUK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
TechnologyBattery storageUK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
TechnologySolarUK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
Grid operatorEastern Power Networks plc (UK Power Networks, East England licence area)UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
Queue date17 Jan 2022UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
Voltage132 kVUK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
Coordinates52.6871, 0.0786UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026

Research on this grid connection and its holder.Who holds it up to the parent company, the project behind it and its connection date, and an introduction to the holder.

How it compares

(ANM) East Of Guanockgate Road grid connection is the 476th-largest of 3,539 grid connections in England and the 605th-largest of 4,870 in the United Kingdom by capacity; its 78 MW is <0.1% of the 467,981 MW we hold for the United Kingdom. Ranks and totals cover the grid connections in our data that report their capacity, not every one in existence.

WithinRankTotalShare
England476th of 3,539341,715 MW<0.1%
United Kingdom605th of 4,870467,981 MW<0.1%
All grid connections in our data3,500th of 8,6181,355,288 MW<0.1%

Nearby

Within 50 km of this grid connection: 304 power plants (119 operating, 3,928 MW), 65 substations, 4 data centers and 3 transmission lines, measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.

NameKindSizeStatusDistance
Tydd Solar FarmPower plant25 MWCancelled0.2 km
Tydd Solar FarmPower plant15 MWCancelled0.2 km
Tydd Solar FarmPower plant25 MWCancelled0.2 km
Leverington Primary 11kVSubstation——4.5 km
Wisbech Railway Primary 11kVSubstation——6.6 km
Guyhirn Primary 11kVSubstation——7.7 km
Positive ParkData center——12 km
Kings Lynn B Connection ProjectTransmission line—Permitted20 km
Longmarsh Green EnergyData center—Planned20 km

Holder, grid operator and place

Other grid connections in England

All 4837 grid connections in England, United Kingdom