Power plant · Warrington, England, United Kingdom

Arpley Landfill Scheme 'B'

Arpley Landfill Scheme 'B' is a power plant in Warrington, England, United Kingdom, with 7.9 MW of capacity, operated by Novera.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationWarrington (coordinates), EnglandDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
AddressOff Liverpool Road Sankey Bridges CheshireDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
StatusOperating (operational)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Start year1999DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Permit date14 Jul 1999 (Town and Country Planning Act, issued by Warrington)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Application date15 Apr 1999 (planning authority Warrington)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Decision date14 Jul 1999 (granted, planning authority Warrington)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
OperatorNoveraDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Capacity7.9 MWDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
TechnologyLandfill GasDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Coordinates53.3727, -2.6405DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026

Research on this power plant and its operator.Who owns it up to the parent company, its grid connection and planning status, and an introduction to the operator.

Request research

Latest events

Dated events about this power plant from official notices and registers, newest first. All recent changes.

  1. Commissioned
  2. Permit granted (planning authority Warrington)
  3. Permit applied for (planning authority Warrington)

How it compares

Arpley Landfill Scheme 'B' is the 1,407th-largest of 3,430 power plants in England and the 2,253rd-largest of 5,050 in the United Kingdom by capacity; its 7.9 MW is <0.1% of the 115,622 MW we hold for the United Kingdom. Ranks and totals cover the power plants in our data that report their capacity, not every one in existence. Power plants planned, permitted or under construction are ranked apart.

WithinRankTotalShare
England1,407th of 3,43071,965 MW<0.1%
United Kingdom2,253rd of 5,050115,622 MW<0.1%
All power plants in our data7,707th of 12,0321,190,447 MW<0.1%

Timeline

Dated facts about this power plant from its sources, oldest first.

  1. Started operating

Nearby

Within 50 km of this power plant: 314 grid connections (175 operating, 1,564 MW), 312 substations, 18 data centers and 3 gas storage facilities, measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.

NameKindSizeStatusDistance
Iron MountainData center——4.7 km
Verizon WarringtonData center——5.9 km
Bold GSPSubstation——7.7 km
The Babbage CentreData center——8.3 km
Unit 1 Junction Lane grid connectionGrid connection5.26 MWPlanned8.4 km
Parkside Railway Station grid connectionGrid connection3 MWOperating8.7 km
Newton Le WillowsSubstation——9.7 km
Lymes Wood Landfill Site grid connectionGrid connection1.03 MWOperating10 km
RisleySubstation——10 km

Operator and place

More from Novera

Other power plants in England

All 5809 power plants in England, United Kingdom