Grid connection · Wales, United Kingdom

Wern Ddu grid connection

Wern Ddu grid connection is a grid connection in Wales, United Kingdom, with 12 MW of capacity, held by Bridge Wind Management Ltd.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationWales (connects at Holywell GT1 / Rhyl GT1 / St Asaph GT2 / St Asaph GT4)SP Energy Networks open data portal · CC BY 4.0 · checked 24 Oct 2026
StatusOperating (connected)SP Energy Networks open data portal · CC BY 4.0 · checked 24 Oct 2026
HolderBridge Wind Management LtdSP Energy Networks open data portal · CC BY 4.0 · checked 24 Oct 2026
Capacity12 MWSP Energy Networks open data portal · CC BY 4.0 · checked 24 Oct 2026
TechnologyWindSP Energy Networks open data portal · CC BY 4.0 · checked 24 Oct 2026
Grid operatorSP ManwebSP Energy Networks open data portal · CC BY 4.0 · checked 24 Oct 2026
Connection date23 Apr 2010SP Energy Networks open data portal · CC BY 4.0 · checked 24 Oct 2026
Voltage33 kVSP Energy Networks open data portal · CC BY 4.0 · checked 24 Oct 2026

Research on this grid connection and its holder.Who holds it up to the parent company, the project behind it and its connection date, and an introduction to the holder.

Request research

How it compares

Wern Ddu grid connection is the 73rd-largest of 158 grid connections in Wales and the 2,022nd-largest of 3,903 in the United Kingdom by capacity; its 12 MW is <0.1% of the 446,745 MW we hold for the United Kingdom. Ranks and totals cover the grid connections in our data that report their capacity, not every one in existence.

WithinRankTotalShare
Wales73rd of 15821,044 MW<0.1%
United Kingdom2,022nd of 3,903446,745 MW<0.1%
All grid connections in our data5,863rd of 7,9281,372,494 MW<0.1%

Holder, grid operator and place

Other grid connections in Wales

All 472 grid connections in Wales, United Kingdom

Data on this page