Grid connection · Wales, United Kingdom

Dinorwig grid connection

Dinorwig grid connection is a grid connection in Wales, United Kingdom, with 1,644 MW of capacity, held by First Hydro Company.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationWales (connects at Dinorwig 400kV Substation)NESO TEC Register · NESO Open Data Licence v1.0 · checked 24 Oct 2026
StatusOperating (built)NESO TEC Register · NESO Open Data Licence v1.0 · checked 24 Oct 2026
HolderFirst Hydro CompanyNESO TEC Register · NESO Open Data Licence v1.0 · checked 24 Oct 2026
Attached toDinorwigNESO TEC Register · NESO Open Data Licence v1.0 · checked 24 Oct 2026
Capacity1,644 MWNESO TEC Register · NESO Open Data Licence v1.0 · checked 24 Oct 2026
TechnologyPump StorageNESO TEC Register · NESO Open Data Licence v1.0 · checked 24 Oct 2026
Grid operatorNational Grid Electricity Transmission plcNESO TEC Register · NESO Open Data Licence v1.0 · checked 24 Oct 2026

Research on this grid connection and its holder.Who holds it up to the parent company, the project behind it and its connection date, and an introduction to the holder.

Request research

How it compares

Dinorwig grid connection is the 2nd-largest of 158 grid connections in Wales and the 37th-largest of 3,903 in the United Kingdom by capacity; its 1,644 MW is 0.37% of the 446,745 MW we hold for the United Kingdom. Ranks and totals cover the grid connections in our data that report their capacity, not every one in existence.

WithinRankTotalShare
Wales2nd of 15821,044 MW7.8%
United Kingdom37th of 3,903446,745 MW0.37%
All grid connections in our data54th of 7,6161,281,251 MW0.13%

Holder, grid operator and place

More from First Hydro Company

Other grid connections in Wales

All 472 grid connections in Wales, United Kingdom

Data on this page