Olrig Mains Farm Wind and BESS grid connection

Olrig Mains Farm Wind and BESS grid connection is a planned grid connection in Scotland, United Kingdom, with 34.4 MW of capacity, held by Green Switch Capital Limited.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
Name in the sourceOLRIG MAINS FARM WIND AND BESS grid connectionSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
LocationScotland (connection site: THURSO SOUTH GRID)SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
StatusPlanned (ACCEPTED TO CONNECT)SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
HolderGreen Switch Capital LimitedSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Attached toThurso South GSP (via: primary)SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Capacity34.4 MWSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
TechnologyBattery storageSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Grid operatorScottish Hydro Electric Power Distribution plcSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Queue date10 Oct 2023SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Connection date31 Oct 2033 (target energisation)SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Voltage33 kVSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Coordinates58.5773, -3.4016SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026

Know more about this grid connection, or want an introduction to its holder? Ask us.

How it compares

Olrig Mains Farm Wind and BESS grid connection is the 398th-largest of 1,192 grid connections in Scotland and the 1,283rd-largest of 3,903 in the United Kingdom by capacity; its 34.4 MW is <0.1% of the 446,745 MW we hold for the United Kingdom. Ranks and totals cover the grid connections in our data that report their capacity, not every one in existence.

WithinRankTotalShare
Scotland398th of 1,19288,894 MW<0.1%
United Kingdom1,283rd of 3,903446,745 MW<0.1%
All grid connections in our data4,491st of 7,6161,281,251 MW<0.1%

Timeline

Dated facts about this grid connection from its sources, oldest first.

  1. Entered the connection queue
  2. Due to connect

Nearby

Within 50 km of this grid connection: 126 power plants (32 operating, 591 MW) and 20 substations, measured from the coordinates in the facts above. The table shows the nearest 6, up to 3 per kind.

NameKindSizeStatusDistance
Oak Tree Cottage, Castletown - Wind TurbinePower plant4.26 MWPlanned2.3 km
Durran MainsPower plant19.5 MWCancelled2.8 km
Hoy FarmPower plant2.3 MWCancelled4.1 km
Mount Pleasant PrimarySubstation——6.1 km
Thurso South GSPSubstation——6.4 km
Ormlie PrimarySubstation——7.9 km