Grid connection · Scotland, United Kingdom

Kinnon Park grid connection

Kinnon Park grid connection is a planned grid connection in Scotland, United Kingdom, with 56.9 MW of capacity, held by Certus Utility Consulting Ltd.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
Name in the sourceKINNON PARK grid connectionSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
LocationScotland (connects at Burghmuir Grid)SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
StatusPlanned (accepted to connect)SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
HolderCertus Utility Consulting LtdSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Attached toBurghmuir Primary (via a primary substation)SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Attached toKinnon Park Farm, Methven - Solar Farm & Battery Storage (matched by shared name+coordinates+technology+capacity, 1.75 km away)Rare Context entity resolution · CC0 1.0 · checked 24 Oct 2026
Capacity56.9 MWSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
TechnologySolarSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Grid operatorScottish Hydro Electric Power Distribution plcSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Queue date28 Sept 2022SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Connection date30 May 2029 (target energisation)SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Voltage33 kVSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Coordinates56.3961, -3.5386SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026

Research on this grid connection and its holder.Who holds it up to the parent company, the project behind it and its connection date, and an introduction to the holder.

Request research

Latest events

Dated events about this grid connection and the records linked to it from official notices and registers, newest first. All recent changes.

  1. Permit refused: Kinnon Park Farm, Methven - Solar Farm & Battery Storage (planning authority Perth and Kinross, reference 24/01188/FLM)
  2. Permit applied for: Kinnon Park Farm, Methven - Solar Farm & Battery Storage (planning authority Perth and Kinross, reference 24/01188/FLM)

How it compares

Kinnon Park grid connection is the 155th-largest of 1,192 grid connections in Scotland and the 712th-largest of 3,903 in the United Kingdom by capacity; its 56.9 MW is <0.1% of the 446,745 MW we hold for the United Kingdom. Ranks and totals cover the grid connections in our data that report their capacity, not every one in existence.

WithinRankTotalShare
Scotland155th of 1,19288,894 MW<0.1%
United Kingdom712th of 3,903446,745 MW<0.1%
All grid connections in our data3,909th of 7,9281,372,494 MW<0.1%

Timeline

Dated facts about this grid connection from its sources, oldest first.

  1. Entered the connection queue
  2. Due to connect

Nearby

Within 50 km of this grid connection: 289 power plants (70 operating, 1,100 MW) and 70 substations, measured from the coordinates in the facts above. The table shows the nearest 6, up to 3 per kind.

NameKindSizeStatusDistance
Taigh An Struith, Tibbermore - Battery Energy StoragePower plant49.9 MWCancelled0.9 km
Dupplin Solar - Solar ArrayPower plant97.5 MWPlanned1.2 km
Kinnon Park Farm, Methven - Solar Farm & Battery StoragePower plant49.9 MWCancelled1.7 km
Burghmuir PrimarySubstation——3.1 km
Burghmuir GSPSubstation——3.1 km
Inveralmond PrimarySubstation——4.2 km

Holder, grid operator and place

More from Certus Utility Consulting Ltd

Other grid connections in Scotland

All 1192 grid connections in Scotland, United Kingdom

Data on this page