Grid connection · Scotland, United Kingdom

Challoch Solar Farm grid connection

Challoch Solar Farm grid connection is a planned grid connection in Scotland, United Kingdom, with 22 MW of capacity, held by Grupotec Renewables Ltd.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationScotland (connects at Newton Stewart)SP Energy Networks open data portal · CC BY 4.0 · checked 24 Oct 2026
StatusPlanned (accepted to connect)SP Energy Networks open data portal · CC BY 4.0 · checked 24 Oct 2026
HolderGrupotec Renewables LtdSP Energy Networks open data portal · CC BY 4.0 · checked 24 Oct 2026
Capacity22 MWSP Energy Networks open data portal · CC BY 4.0 · checked 24 Oct 2026
TechnologySolarSP Energy Networks open data portal · CC BY 4.0 · checked 24 Oct 2026
TechnologyBattery storageSP Energy Networks open data portal · CC BY 4.0 · checked 24 Oct 2026
Grid operatorSP Distribution plcSP Energy Networks open data portal · CC BY 4.0 · checked 24 Oct 2026
Queue date2 Dec 2022SP Energy Networks open data portal · CC BY 4.0 · checked 24 Oct 2026
Connection date1 Aug 2028 (target energisation)SP Energy Networks open data portal · CC BY 4.0 · checked 24 Oct 2026
Voltage33 kVSP Energy Networks open data portal · CC BY 4.0 · checked 24 Oct 2026

Research on this grid connection and its holder.Who holds it up to the parent company, the project behind it and its connection date, and an introduction to the holder.

Request research

How it compares

Challoch Solar Farm grid connection is the 534th-largest of 1,192 grid connections in Scotland and the 1,574th-largest of 3,903 in the United Kingdom by capacity; its 22 MW is <0.1% of the 446,745 MW we hold for the United Kingdom. Ranks and totals cover the grid connections in our data that report their capacity, not every one in existence.

WithinRankTotalShare
Scotland534th of 1,19288,894 MW<0.1%
United Kingdom1,574th of 3,903446,745 MW<0.1%
All grid connections in our data5,163rd of 7,9281,372,494 MW<0.1%

Timeline

Dated facts about this grid connection from its sources, oldest first.

  1. Entered the connection queue
  2. Due to connect

Holder, grid operator and place

Other grid connections in Scotland

All 1192 grid connections in Scotland, United Kingdom

Data on this page