Grid connection · Scotland, United Kingdom

Cameron Bridge Distillery CHP grid connection

Cameron Bridge Distillery CHP grid connection is a grid connection in Scotland, United Kingdom, with 7.11 MW of capacity, held by Diageo Great Britain Limited.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationScotland (connects at LEVEN (11kV))SP Energy Networks open data portal · CC BY 4.0 · checked 24 Oct 2026
StatusOperating (connected)SP Energy Networks open data portal · CC BY 4.0 · checked 24 Oct 2026
HolderDiageo Great Britain LimitedSP Energy Networks open data portal · CC BY 4.0 · checked 24 Oct 2026
Capacity7.11 MWSP Energy Networks open data portal · CC BY 4.0 · checked 24 Oct 2026
Grid operatorSP Distribution plcSP Energy Networks open data portal · CC BY 4.0 · checked 24 Oct 2026
Connection date26 Nov 2010SP Energy Networks open data portal · CC BY 4.0 · checked 24 Oct 2026
Voltage11 kVSP Energy Networks open data portal · CC BY 4.0 · checked 24 Oct 2026

Research on this grid connection and its holder.Who holds it up to the parent company, the project behind it and its connection date, and an introduction to the holder.

Request research

How it compares

Cameron Bridge Distillery CHP grid connection is the 762nd-largest of 1,192 grid connections in Scotland and the 2,364th-largest of 3,903 in the United Kingdom by capacity; its 7.11 MW is <0.1% of the 446,745 MW we hold for the United Kingdom. Ranks and totals cover the grid connections in our data that report their capacity, not every one in existence.

WithinRankTotalShare
Scotland762nd of 1,19288,894 MW<0.1%
United Kingdom2,364th of 3,903446,745 MW<0.1%
All grid connections in our data6,306th of 7,9281,372,494 MW<0.1%

Holder, grid operator and place

More from Diageo Great Britain Limited

Other grid connections in Scotland

All 1192 grid connections in Scotland, United Kingdom

Data on this page