Grid connection · England, United Kingdom

Waste 82 MW grid connection at Fryston Lane Direct

Waste 82 MW grid connection at Fryston Lane Direct is a grid connection in England, United Kingdom, with 82 MW of capacity, connected by Northern Powergrid (Yorkshire) plc.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationEngland (connects at Fryston Lane Direct)Northern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
StatusOperating (connected)Northern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
Attached toFerrybridge B (via a grid supply point)Northern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
Capacity82 MWNorthern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
TechnologyWasteNorthern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
Grid operatorNorthern Powergrid (Yorkshire) plcNorthern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
Connection date18 Jun 2015Northern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
Voltage132 kVNorthern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
Coordinates53.7208, -1.2835Northern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026

Research on this grid connection and its holder.Who holds it up to the parent company, the project behind it and its connection date, and an introduction to the holder.

Request research

How it compares

Waste 82 MW grid connection at Fryston Lane Direct is the 407th-largest of 2,533 grid connections in England and the 534th-largest of 3,903 in the United Kingdom by capacity; its 82 MW is <0.1% of the 446,745 MW we hold for the United Kingdom. Ranks and totals cover the grid connections in our data that report their capacity, not every one in existence.

WithinRankTotalShare
England407th of 2,533319,370 MW<0.1%
United Kingdom534th of 3,903446,745 MW<0.1%
All grid connections in our data3,497th of 7,9281,372,494 MW<0.1%

Nearby

Within 50 km of this grid connection: 436 power plants (123 operating, 9,384 MW), 384 substations, 11 data centers and 2 transmission lines, measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.

NameKindSizeStatusDistance
Ferrybridge Multifuel 2 (FM2) Power StationPower plant90 MWPermitted0.2 km
Kirkhaw LaneSubstation——0.4 km
Ferrybridge Multifuel 1 (FM1)Power plant68 MWOperating0.5 km
Ferrybridge Multifuel 2 (FM2)Power plant70 MWOperating0.5 km
Ferrybridge ASubstation——0.9 km
Ferrybridge A 11kVSubstation——0.9 km
HSBC Wakefield Data CentreData center——6.5 km
nLighten LeedsData center——7.9 km
Yorkshire GREENTransmission line—Permitted20 km

Grid operator and place