Grid connection · England, United Kingdom
Vauxhall B (Booston Wood) grid connection
Vauxhall B (Booston Wood) grid connection is a grid connection in England, United Kingdom, with 20 MW of capacity, held by UK Power Reserve.
Facts
Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.
| Fact | Value | Source |
|---|---|---|
| Location | England (connects at Bromborough GT2 / Ellesmere Port GT1 / Hooton PK GT1A / Hooton PK GT2A) | SP Energy Networks open data portal · CC BY 4.0 · checked 24 Oct 2026 |
| Status | Operating (connected) | SP Energy Networks open data portal · CC BY 4.0 · checked 24 Oct 2026 |
| Holder | UK Power Reserve | SP Energy Networks open data portal · CC BY 4.0 · checked 24 Oct 2026 |
| Capacity | 20 MW | SP Energy Networks open data portal · CC BY 4.0 · checked 24 Oct 2026 |
| Technology | Battery storage | SP Energy Networks open data portal · CC BY 4.0 · checked 24 Oct 2026 |
| Grid operator | SP Manweb | SP Energy Networks open data portal · CC BY 4.0 · checked 24 Oct 2026 |
| Voltage | 33 kV | SP Energy Networks open data portal · CC BY 4.0 · checked 24 Oct 2026 |
Research on this grid connection and its holder.Who holds it up to the parent company, the project behind it and its connection date, and an introduction to the holder.
Request researchHow it compares
Vauxhall B (Booston Wood) grid connection is the 1,020th-largest of 2,533 grid connections in England and the 1,645th-largest of 3,903 in the United Kingdom by capacity; its 20 MW is <0.1% of the 446,745 MW we hold for the United Kingdom. Ranks and totals cover the grid connections in our data that report their capacity, not every one in existence.
| Within | Rank | Total | Share |
|---|---|---|---|
| England | 1,020th of 2,533 | 319,370 MW | <0.1% |
| United Kingdom | 1,645th of 3,903 | 446,745 MW | <0.1% |
| All grid connections in our data | 5,244th of 7,928 | 1,372,494 MW | <0.1% |
Holder, grid operator and place
More from UK Power Reserve
- Land off Queenborough Road40 MW · under construction
- Asfordby Business Park (1)23.4 MW
- Bristol Road20 MW
- Beaufort Road20 MW
- Oil Sites Road9.6 MW · permitted
Other grid connections in England
- Bute Hydrogen Project 1 grid connection4,800 MW
- Drax BECCS grid connection3,906 MW
- Drax Power Station grid connection3,906 MW
- Bute Hydrogen Project 2 grid connection3,600 MW
- Bute Hydrogen Project 3 grid connection3,600 MW
- Bute Hydrogen Project 5 grid connection3,600 MW
- Bute Hydrogen Project 6 grid connection3,600 MW
- Hinkley Point C grid connection3,340 MW
Data on this page
- California ISO. CAISO queue report, CAISO Privacy and Terms of Use.
- SP Electricity North West, via Northern Powergrid Open Data. SP Electricity North West open data portal, CC BY 4.0.
- ERCOT GIS report. ERCOT GIS report, ERCOT Terms of Use.
- Supported by National Energy SO Open Data. NESO TEC Register, NESO Open Data Licence v1.0.
- Supported by Northern Powergrid Open Data. Northern Powergrid open data portal, Northern Powergrid Open Data Licence v1.0.
- NYISO interconnection queue. NYISO interconnection queue, Free reuse.
- PJM New Services Queue. PJM New Services Queue, Free reuse.
- SP Energy Networks, via Northern Powergrid Open Data. SP Energy Networks open data portal, CC BY 4.0.
- SSEN Distribution. SSEN Distribution data portal, CC BY 4.0.