Grid connection · England, United Kingdom
Unipart Group of Companies grid connection
Unipart Group of Companies grid connection is a planned grid connection in England, United Kingdom, with 2.4 MW of capacity, connected by Southern Electric Power Distribution plc.
Facts
Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.
| Fact | Value | Source |
|---|---|---|
| Name in the source | UNIPART GROUP OF COMPANIES grid connection | SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026 |
| Location | England (connects at Cowley Local) | SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026 |
| Status | Planned (accepted to connect) | SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026 |
| Attached to | Cowley Local Primary (via a primary substation) | SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026 |
| Capacity | 2.4 MW | SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026 |
| Technology | Solar | SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026 |
| Grid operator | Southern Electric Power Distribution plc | SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026 |
| Queue date | 4 Sept 2025 | SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026 |
| Connection date | 31 Dec 2030 (target energisation) | SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026 |
| Voltage | 11 kV | SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026 |
| Coordinates | 51.7297, -1.1849 | SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026 |
Research on this grid connection and its grid operator.Who holds it up to the parent company, the project behind it and its connection date, and an introduction to the grid operator.
Request researchHow it compares
Unipart Group of Companies grid connection is the 2,096th-largest of 2,533 grid connections in England and the 3,207th-largest of 3,903 in the United Kingdom by capacity; its 2.4 MW is <0.1% of the 446,745 MW we hold for the United Kingdom. Ranks and totals cover the grid connections in our data that report their capacity, not every one in existence.
| Within | Rank | Total | Share |
|---|---|---|---|
| England | 2,096th of 2,533 | 319,370 MW | <0.1% |
| United Kingdom | 3,207th of 3,903 | 446,745 MW | <0.1% |
| All grid connections in our data | 7,211th of 7,928 | 1,372,494 MW | <0.1% |
Timeline
Dated facts about this grid connection from its sources, oldest first.
- Entered the connection queue
- Due to connect
Nearby
Within 50 km of this grid connection: 329 power plants (114 operating, 1,687 MW), 174 substations and 62 data centers, measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.
| Name | Kind | Size | Status | Distance |
|---|---|---|---|---|
| BMW UK Manufacturing Ltd | Power plant | 3 MW | Operating | 0.6 km |
| Cowley Local (Main) BSP | Substation | — | — | 0.7 km |
| Cowley Local (Reserve) BSP | Substation | — | — | 0.7 km |
| Cowley Local Primary | Substation | — | — | 0.7 km |
| Cowley electricity sub-station | Power plant | 49.9 MW | Operating | 1.3 km |
| Lower road, Garsington - Energy Storage System | Power plant | 100 MW | Cancelled | 2.3 km |
| University Shared Data Centre | Data center | — | — | 5.7 km |
| AWS Didcot Data Centre | Data center | — | — | 14 km |
| R89 | Data center | — | — | 20 km |
Grid operator and place
More from Southern Electric Power Distribution plc
- Weston Lane (G) grid connection450 MW
- 200MW BESS grid connection200 MW
- 200MW BESS grid connection200 MW
- Ready - 200MW Battery grid connection200 MW
- Witney Bypass - 150MW BESS grid connection160 MW
- Norrington Gate Battery 150MW grid connection150 MW
- Stonehill grid connection150 MW
- Fawley North Cogeneration Connection grid connection138 MW
Other grid connections in England
- Bute Hydrogen Project 1 grid connection4,800 MW
- Drax BECCS grid connection3,906 MW
- Drax Power Station grid connection3,906 MW
- Bute Hydrogen Project 2 grid connection3,600 MW
- Bute Hydrogen Project 3 grid connection3,600 MW
- Bute Hydrogen Project 5 grid connection3,600 MW
- Bute Hydrogen Project 6 grid connection3,600 MW
- Hinkley Point C grid connection3,340 MW
Data on this page
- California ISO. CAISO queue report, CAISO Privacy and Terms of Use.
- Contains public sector information licensed under the Open Government Licence v3.0. DESNZ Renewable Energy Planning Database (REPD), Open Government Licence v3.0.
- SP Electricity North West, via Northern Powergrid Open Data. SP Electricity North West open data portal, CC BY 4.0.
- ERCOT GIS report. ERCOT GIS report, ERCOT Terms of Use.
- Supported by National Energy SO Open Data. NESO TEC Register, NESO Open Data Licence v1.0.
- Supported by Northern Powergrid Open Data. Northern Powergrid open data portal, Northern Powergrid Open Data Licence v1.0.
- NYISO interconnection queue. NYISO interconnection queue, Free reuse.
- © OpenStreetMap contributors. OpenStreetMap data centers, ODbL 1.0.
- PJM New Services Queue. PJM New Services Queue, Free reuse.
- SP Energy Networks, via Northern Powergrid Open Data. SP Energy Networks open data portal, CC BY 4.0.
- SSEN Distribution. SSEN Distribution data portal, CC BY 4.0.