RARE CONTEXT Request research

Grid connection · England, United Kingdom

Pitstock Farm grid connection

Pitstock Farm grid connection is a planned grid connection in England, United Kingdom, with 40.8 MW of capacity, held by Voltalia UK.

Map: where Pitstock Farm grid connection lies
51.3081, 0.7491 on OpenStreetMap

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationEngland (connects at Sittingbourne Grid 33kV)UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
StatusPlanned (accepted to connect)UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
HolderVoltalia UKUK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
Attached toPitstock Farm - Solar Photovoltaic Panels (matched by shared name+coordinates+technology+capacity+company, 0.24 km away)Rare Context entity resolution · CC0 1.0 · checked 25 Oct 2026
Attached toSittingbourne Grid 33kV (via a primary substation)UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
Capacity40.8 MWUK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
TechnologyBattery storageUK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
TechnologySolarUK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
Grid operatorSouth Eastern Power Networks plc (UK Power Networks, South East England licence area)UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
Queue date16 Dec 2022UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
Connection date31 Oct 2036 (target energisation)UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
Voltage33 kVUK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026
Coordinates51.3081, 0.7491UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026

Research on this grid connection and its holder.Who holds it up to the parent company, the project behind it and its connection date, and an introduction to the holder.

Latest events

Dated events about this grid connection and the records linked to it from official notices, registers and owners' press releases, newest first. All recent changes.

  1. Permit granted: Pitstock Farm - Solar Photovoltaic Panels (planning authority Swale, reference 24/500125/FULL)
  2. Permit applied for: Pitstock Farm - Solar Photovoltaic Panels (planning authority Swale, reference 24/500125/FULL)

How it compares

Pitstock Farm grid connection is the 907th-largest of 3,539 grid connections in England and the 1,292nd-largest of 4,870 in the United Kingdom by capacity; its 40.8 MW is <0.1% of the 467,981 MW we hold for the United Kingdom. Ranks and totals cover the grid connections in our data that report their capacity, not every one in existence.

WithinRankTotalShare
England907th of 3,539341,715 MW<0.1%
United Kingdom1,292nd of 4,870467,981 MW<0.1%
All grid connections in our data4,538th of 8,6181,355,288 MW<0.1%

Timeline

Dated facts about this grid connection from its sources, oldest first.

  1. Entered the connection queue
  2. Due to connect

Nearby

Within 50 km of this grid connection: 323 power plants (122 operating, 6,956 MW), 219 substations, 10 data centers and 1 transmission line, measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.

NameKindSizeStatusDistance
Pitstock Farm - Solar Photovoltaic PanelsPower plant41 MWPermitted0.2 km
Sota DatacentreData center——1.7 km
Sittingbourne Town 11kVSubstation——3.7 km
Vigo Lane, Borden - Solar FarmPower plant40 MWPermitted4.2 km
Sittingbourne West 11kVSubstation——4.4 km
Plot 2B EurolinkVPower plant20 MWUnder construction4.6 km
Sittingbourne Grid 33kVSubstation——5.4 km
CustodianDC MaidstoneData center——14 km
CXD Infrastructure SolutionsData center——14 km

Holder, grid operator and place

More from Voltalia UK

Other grid connections in England

All 4837 grid connections in England, United Kingdom

Data on this page