Grid connection · England, United Kingdom

Flaxlands Manor Farm grid connection

Flaxlands Manor Farm grid connection is a planned grid connection in England, United Kingdom, with 115 MW of capacity, connected by Southern Electric Power Distribution plc.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
Name in the sourceFLAXLANDS MANOR FARM grid connectionSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
LocationEngland (connects at Swindon)SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
StatusPlanned (accepted to connect)SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Attached toSwindon BSP (via a bulk supply point)SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Capacity115 MWSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Grid operatorSouthern Electric Power Distribution plcSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Queue date14 Aug 2024SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Connection date22 Jun 2037 (target energisation)SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Voltage132 kVSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Coordinates51.5642, -1.9052SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026

Research on this grid connection and its grid operator.Who holds it up to the parent company, the project behind it and its connection date, and an introduction to the grid operator.

Request research

How it compares

Flaxlands Manor Farm grid connection is the 287th-largest of 2,533 grid connections in England and the 382nd-largest of 3,903 in the United Kingdom by capacity; its 115 MW is <0.1% of the 446,745 MW we hold for the United Kingdom. Ranks and totals cover the grid connections in our data that report their capacity, not every one in existence.

WithinRankTotalShare
England287th of 2,533319,370 MW<0.1%
United Kingdom382nd of 3,903446,745 MW<0.1%
All grid connections in our data2,877th of 7,9281,372,494 MW<0.1%

Timeline

Dated facts about this grid connection from its sources, oldest first.

  1. Entered the connection queue
  2. Due to connect

Nearby

Within 50 km of this grid connection: 377 power plants (136 operating, 2,232 MW), 124 substations, 10 data centers and 1 AI supercomputer, measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.

NameKindSizeStatusDistance
Park Grounds FarmPower plant5 MWCancelled1.7 km
Swindon Energy Plant (Park Grounds)Power plant6 MWUnder construction1.7 km
Spittleborough FarmPower plant12 MWOperating2.7 km
Wootton Bassett PrimarySubstation——4.0 km
Galileo PrimarySubstation——4.1 km
VodafoneData center——4.3 km
Nationwide Swindon Technology CentreData center——4.8 km
Swindon PrimarySubstation——6.1 km
AWS Swindon Data CentreData center——11 km

Grid operator and place

More from Southern Electric Power Distribution plc

Other grid connections in England

All 3831 grid connections in England, United Kingdom

Data on this page