Down Barn Farm PV Solar Park grid connection

Down Barn Farm PV Solar Park grid connection is a planned grid connection in England, United Kingdom, with 40 MW of capacity, held by Lightsource Renewable UK Development Ltd.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
Name in the sourceDOWN BARN FARM PV SOLAR PARK grid connectionSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
LocationEngland (connects at Amesbury)SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
StatusPlanned (accepted to connect)SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
HolderLightsource Renewable UK Development LtdSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Attached toDown Barn Farm (matched by name+coordinates+technology+capacity, 1.43 km away)Rare Context entity resolution · CC0 1.0 · checked 24 Oct 2026
Attached toAmesbury BSP (via a bulk supply point)SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Capacity40 MWSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
TechnologySolarSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Grid operatorSouthern Electric Power Distribution plcSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Queue date21 Aug 2019SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Connection date22 Dec 2027 (target energisation)SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Voltage132 kVSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Coordinates51.1848, -1.6682SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026

Research on this grid connection and its holder.Who holds it up to the parent company, the project behind it and its connection date, and an introduction to the holder.

Request research

Latest events

Dated events about this grid connection and the records linked to it from official notices and registers, newest first. All recent changes.

  1. Permit granted: Down Barn Farm (planning authority Wiltshire, reference 19/10890/FUL)
  2. Permit applied for: Down Barn Farm (planning authority Wiltshire, reference 19/10890/FUL)

How it compares

Down Barn Farm PV Solar Park grid connection is the 740th-largest of 2,533 grid connections in England and the 1,138th-largest of 3,903 in the United Kingdom by capacity; its 40 MW is <0.1% of the 446,745 MW we hold for the United Kingdom. Ranks and totals cover the grid connections in our data that report their capacity, not every one in existence.

WithinRankTotalShare
England740th of 2,533319,370 MW<0.1%
United Kingdom1,138th of 3,903446,745 MW<0.1%
All grid connections in our data4,573rd of 7,9281,372,494 MW<0.1%

Timeline

Dated facts about this grid connection from its sources, oldest first.

  1. Entered the connection queue
  2. Due to connect

Nearby

Within 50 km of this grid connection: 322 power plants (134 operating, 1,419 MW), 193 substations and 13 data centers, measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.

NameKindSizeStatusDistance
Park House PrimarySubstation——0.9 km
Shipton Bellinger - Park House Corner Solar FarmPower plant5.4 MWOperating1.2 km
Parkhouse Corner (Orta Solar)Power plant6.6 MWOperating1.3 km
Down Barn FarmPower plant49.9 MWPermitted1.4 km
Boscombe Down PrimarySubstation——6.4 km
Thruxton PrimarySubstation——6.5 km
Sky ChilworthData center——30 km
Venture WestData center——34 km
AWS Swindon Data CentreData center——38 km

Holder, grid operator and place

More from Lightsource Renewable UK Development Ltd

Other grid connections in England

All 3831 grid connections in England, United Kingdom

Data on this page