Grid connection · England, United Kingdom
Clifton Marsh grid connection
Clifton Marsh grid connection is a planned grid connection in England, United Kingdom, with 49.9 MW of capacity, connected by Electricity North West Limited.
Facts
Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.
| Fact | Value | Source |
|---|---|---|
| Name in the source | CLIFTON MARSH grid connection | SP Electricity North West open data portal · CC BY 4.0 · checked 24 Oct 2026 |
| Location | England (connects at Penwortham West GSP / Stanah GSP Group) | SP Electricity North West open data portal · CC BY 4.0 · checked 24 Oct 2026 |
| Status | Planned (accepted to connect) | SP Electricity North West open data portal · CC BY 4.0 · checked 24 Oct 2026 |
| Attached to | Clifton Marsh Farm, Preston New Road - Solar Farm (matched by shared name+coordinates+technology+capacity, 0.06 km away) | Rare Context entity resolution · CC0 1.0 · checked 24 Oct 2026 |
| Capacity | 49.9 MW | SP Electricity North West open data portal · CC BY 4.0 · checked 24 Oct 2026 |
| Technology | Solar | SP Electricity North West open data portal · CC BY 4.0 · checked 24 Oct 2026 |
| Grid operator | Electricity North West Limited | SP Electricity North West open data portal · CC BY 4.0 · checked 24 Oct 2026 |
| Queue date | 10 Jun 2021 | SP Electricity North West open data portal · CC BY 4.0 · checked 24 Oct 2026 |
| Voltage | 132 kV | SP Electricity North West open data portal · CC BY 4.0 · checked 24 Oct 2026 |
| Coordinates | 53.7591, -2.8161 | SP Electricity North West open data portal · CC BY 4.0 · checked 24 Oct 2026 |
Research on this grid connection and its grid operator.Who holds it up to the parent company, the project behind it and its connection date, and an introduction to the grid operator.
Request researchHow it compares
Clifton Marsh grid connection is the 597th-largest of 2,533 grid connections in England and the 904th-largest of 3,903 in the United Kingdom by capacity; its 49.9 MW is <0.1% of the 446,745 MW we hold for the United Kingdom. Ranks and totals cover the grid connections in our data that report their capacity, not every one in existence.
| Within | Rank | Total | Share |
|---|---|---|---|
| England | 597th of 2,533 | 319,370 MW | <0.1% |
| United Kingdom | 904th of 3,903 | 446,745 MW | <0.1% |
| All grid connections in our data | 4,270th of 7,928 | 1,372,494 MW | <0.1% |
Nearby
Within 50 km of this grid connection: 330 power plants (106 operating, 1,710 MW), 280 substations, 10 data centers, 2 transmission lines and 1 gas storage facility, measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.
| Name | Kind | Size | Status | Distance |
|---|---|---|---|---|
| Clifton Marsh Farm, Preston New Road - Solar Farm | Power plant | 49.9 MW | Planned | 0.1 km |
| Clifton Marsh Waste Water Treatment Works | Power plant | 2 MW | Operating | 0.7 km |
| Clifton Marsh Wastewater Treatment Works | Power plant | 1.3 MW | Operating | 0.9 km |
| Hall Cross | Substation | — | — | 4.0 km |
| Penwortham West / Stanah GSP | Substation | — | — | 4.3 km |
| Ashton (Ribble) | Substation | — | — | 4.3 km |
| East Irish Sea Transmission Project | Transmission line | — | Planned | 14 km |
| Morgan and Morecambe Offshore Wind Farms Transmission Assets | Transmission line | — | Permitted | 16 km |
| Preesall Saltfield Underground Gas Storage | Gas storage facility | — | Cancelled | 19 km |
Grid operator and place
More from Electricity North West Limited
- The Albion Academy grid connection416 MW
- Heaten Hall Farm BESS grid connection240 MW
- Heaten Hall Farm BESS+Wind grid connection240 MW
- Houghton BESS grid connection240 MW
- Walney 2 Offshore Wind Farm grid connection183 MW
- Bolton Road grid connection179 MW
- WS Lamb 2 grid connection160 MW
- Ormonde Offshore Windfarm grid connection150 MW
Other grid connections in England
- Bute Hydrogen Project 1 grid connection4,800 MW
- Drax BECCS grid connection3,906 MW
- Drax Power Station grid connection3,906 MW
- Bute Hydrogen Project 2 grid connection3,600 MW
- Bute Hydrogen Project 3 grid connection3,600 MW
- Bute Hydrogen Project 5 grid connection3,600 MW
- Bute Hydrogen Project 6 grid connection3,600 MW
- Hinkley Point C grid connection3,340 MW
Data on this page
- California ISO. The terms cover every document on caiso.com, the cluster reports included. CAISO queue report, CAISO Privacy and Terms of Use.
- DESNZ Renewable Energy Planning Database (REPD). DESNZ Renewable Energy Planning Database (REPD), Open Government Licence v3.0.
- SP Electricity North West, via Northern Powergrid Open Data. SP Electricity North West open data portal, CC BY 4.0.
- ERCOT GIS report. ERCOT GIS report, ERCOT Terms of Use.
- Supported by National Energy SO Open Data. NESO TEC Register, NESO Open Data Licence v1.0.
- Supported by Northern Powergrid Open Data. Northern Powergrid open data portal, Northern Powergrid Open Data Licence v1.0.
- NYISO interconnection queue. NYISO interconnection queue, Free reuse.
- Planning Inspectorate: National Infrastructure Projects. Planning Inspectorate: National Infrastructure Projects, Open Government Licence v3.0.
- PJM New Services Queue. PJM New Services Queue, Free reuse.
- Rare Context entity resolution. Rare Context entity resolution, CC0 1.0.
- SP Energy Networks, via Northern Powergrid Open Data. SP Energy Networks open data portal, CC BY 4.0.
- SSEN Distribution. SSEN Distribution data portal, CC BY 4.0.