Grid connection · England, United Kingdom

Bedhampton BESS grid connection

Bedhampton BESS grid connection is a planned grid connection in England, United Kingdom, with 57 MW of capacity, held by Energy 101 Ltd.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
Name in the sourceBEDHAMPTON BESS grid connectionSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
LocationEngland (connection site: MEYRICK ROAD)SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
StatusPlanned (ACCEPTED TO CONNECT)SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
HolderEnergy 101 LtdSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Attached toMeyrick Road Primary (via: primary)SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Capacity57 MWSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
TechnologyBattery storageSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Grid operatorSouthern Electric Power Distribution plcSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Queue date23 Sept 2022SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Connection date30 Oct 2037 (target energisation)SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Voltage132 kVSSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026
Coordinates50.8535, -0.9992SSEN Distribution data portal · CC BY 4.0 · checked 24 Oct 2026

Know more about this grid connection, or want an introduction to its holder? Ask us.

How it compares

Bedhampton BESS grid connection is the 508th-largest of 2,533 grid connections in England and the 707th-largest of 3,903 in the United Kingdom by capacity; its 57 MW is <0.1% of the 446,745 MW we hold for the United Kingdom. Ranks and totals cover the grid connections in our data that report their capacity, not every one in existence.

WithinRankTotalShare
England508th of 2,533319,370 MW<0.1%
United Kingdom707th of 3,903446,745 MW<0.1%
All grid connections in our data3,629th of 7,6161,281,251 MW<0.1%

Timeline

Dated facts about this grid connection from its sources, oldest first.

  1. Entered the connection queue
  2. Due to connect

Nearby

Within 50 km of this grid connection: 231 power plants (98 operating, 741 MW), 156 substations and 1 transmission line, measured from the coordinates in the facts above. The table shows the nearest 7, up to 3 per kind.

NameKindSizeStatusDistance
Meyrick Road PrimarySubstation——0.3 km
Brockhampton PrimarySubstation——0.7 km
Havant BSPSubstation——0.8 km
Bedhampton Pumping Station, Meyrick Road - Battery Energy StoragePower plant150 MWPlanned1.7 km
Farlington Water Treatment Works, Gillman Road - Solar PanelsPower plant3.68 MWPermitted1.9 km
Dunsbury Park, Fitzwygram Way - Solar PanelsPower plant1.25 MWPermitted2.8 km
Aquind InterconnectorTransmission line—Planned7.7 km

Holder, grid operator and place

Other grid connections in England

All 3831 grid connections in England, United Kingdom

Data on this page