Grid connection · England, United Kingdom

Battery storage and Waste 20 MW grid connection at Hut Green Generation

Battery storage and Waste 20 MW grid connection at Hut Green Generation is a planned grid connection in England, United Kingdom, with 20 MW of capacity, connected by Northern Powergrid (Yorkshire) plc.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationEngland (connects at Hut Green Generation)Northern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
StatusPlanned (accepted to connect)Northern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
Attached toFerrybridge A (via a bulk supply point)Northern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
Capacity20 MWNorthern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
TechnologyBattery storageNorthern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
TechnologyWasteNorthern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
Grid operatorNorthern Powergrid (Yorkshire) plcNorthern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
Queue date19 May 2023Northern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
Voltage66 kVNorthern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
Coordinates53.7019, -1.1557Northern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026

Research on this grid connection and its holder.Who holds it up to the parent company, the project behind it and its connection date, and an introduction to the holder.

Request research

How it compares

Battery storage and Waste 20 MW grid connection at Hut Green Generation is the 1,020th-largest of 2,533 grid connections in England and the 1,645th-largest of 3,903 in the United Kingdom by capacity; its 20 MW is <0.1% of the 446,745 MW we hold for the United Kingdom. Ranks and totals cover the grid connections in our data that report their capacity, not every one in existence.

WithinRankTotalShare
England1,020th of 2,533319,370 MW<0.1%
United Kingdom1,645th of 3,903446,745 MW<0.1%
All grid connections in our data5,244th of 7,9281,372,494 MW<0.1%

Nearby

Within 50 km of this grid connection: 471 power plants (131 operating, 10,876 MW), 371 substations, 11 data centers and 3 transmission lines, measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.

NameKindSizeStatusDistance
Corner Of Weeland Road, Lunn Lane - Battery Storage FacilityPower plant200 MWPermitted1.5 km
Eggborough (Former Abre Biomass Facility)Power plant10 MWCancelled1.6 km
Eggborough Biomass Power StationPower plant10.6 MWCancelled1.8 km
EggboroughSubstation——2.2 km
BealSubstation——3.6 km
Weeland RoadSubstation——5.7 km
HSBC Wakefield Data CentreData center——15 km
nLighten LeedsData center——16 km
ThalesData center——22 km

Grid operator and place

More from Northern Powergrid (Yorkshire) plc

Other grid connections in England

All 3831 grid connections in England, United Kingdom