Grid connection · England, United Kingdom

Battery storage and Solar 88.59 MW grid connection at Parkcliff Farm BESS Direct

Battery storage and Solar 88.59 MW grid connection at Parkcliff Farm BESS Direct is a planned grid connection in England, United Kingdom, with 88.6 MW of capacity, connected by Northern Powergrid (Yorkshire) plc.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationEngland (connects at Parkcliff Farm BESS Direct)Northern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
StatusPlanned (accepted to connect)Northern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
Attached toThurcroft (via a grid supply point)Northern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
Capacity88.6 MWNorthern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
TechnologyBattery storageNorthern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
TechnologySolarNorthern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
Grid operatorNorthern Powergrid (Yorkshire) plcNorthern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
Queue date11 Mar 2024Northern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
Voltage66 kVNorthern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
Coordinates53.4057, -1.2630Northern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026

Research on this grid connection and its grid operator.Who holds it up to the parent company, the project behind it and its connection date, and an introduction to the grid operator.

Request research

How it compares

Battery storage and Solar 88.59 MW grid connection at Parkcliff Farm BESS Direct is the 398th-largest of 2,533 grid connections in England and the 522nd-largest of 3,903 in the United Kingdom by capacity; its 88.6 MW is <0.1% of the 446,745 MW we hold for the United Kingdom. Ranks and totals cover the grid connections in our data that report their capacity, not every one in existence.

WithinRankTotalShare
England398th of 2,533319,370 MW<0.1%
United Kingdom522nd of 3,903446,745 MW<0.1%
All grid connections in our data3,451st of 7,9281,372,494 MW<0.1%

Nearby

Within 50 km of this grid connection: 520 power plants (155 operating, 4,386 MW), 276 substations, 10 data centers and 2 transmission lines, measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.

NameKindSizeStatusDistance
Moat Lane, Wickersley - Battery Storage FacilityPower plant100 MWPermitted0.1 km
ThurcroftSubstation——0.2 km
Moat Lane, Wickersley - Battery Storage FacilityPower plant100 MWPermitted0.2 km
Green Lane, Thurcroft - Battery Energy Storage FacilityPower plant85 MWPermitted0.3 km
New Orchard LaneSubstation——0.7 km
SilverwoodSubstation——4.0 km
Hive ITData center——15 km
ThalesData center——15 km
UoS IT ServicesData center——15 km

Grid operator and place

More from Northern Powergrid (Yorkshire) plc

Other grid connections in England