Grid connection · England, United Kingdom

Battery storage and Solar 47.96 MW grid connection at Stepping Stone Solar and BESS Hybrid Direct

Battery storage and Solar 47.96 MW grid connection at Stepping Stone Solar and BESS Hybrid Direct is a planned grid connection in England, United Kingdom, with 48 MW of capacity, connected by Northern Powergrid (Yorkshire) plc.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationEngland (connection site: Stepping Stone Solar and BESS Hybrid Direct)Northern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
StatusPlanned (Accepted To Connect)Northern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
Attached toWest Melton Section 3 (via: gsp)Northern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
Capacity48 MWNorthern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
TechnologyBattery storageNorthern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
TechnologySolarNorthern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
Grid operatorNorthern Powergrid (Yorkshire) plcNorthern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
Queue date24 Oct 2023Northern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
Voltage132 kVNorthern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
Coordinates53.4594, -1.5169Northern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026

Know more about this grid connection, or want an introduction to its grid operator? Ask us.

How it compares

Battery storage and Solar 47.96 MW grid connection at Stepping Stone Solar and BESS Hybrid Direct is the 684th-largest of 2,533 grid connections in England and the 1,046th-largest of 3,903 in the United Kingdom by capacity; its 48 MW is <0.1% of the 446,745 MW we hold for the United Kingdom. Ranks and totals cover the grid connections in our data that report their capacity, not every one in existence.

WithinRankTotalShare
England684th of 2,533319,370 MW<0.1%
United Kingdom1,046th of 3,903446,745 MW<0.1%
All grid connections in our data4,155th of 7,6161,281,251 MW<0.1%

Nearby

Within 50 km of this grid connection: 477 power plants (147 operating, 4,245 MW), 319 substations and 2 transmission lines, measured from the coordinates in the facts above. The table shows the nearest 8, up to 3 per kind.

NameKindSizeStatusDistance
Sherwin Williams Diversified Brands, Thorncliffe Road - Solar PanelsPower plant1.2 MWPlanned3.7 km
Tankersley ParkSubstation——3.7 km
EcclesfieldSubstation——4.6 km
Claywheels LaneSubstation——4.7 km
Loicher LanePower plant8 MWOperating4.8 km
Yarra Industrial Estate, Loicher Lane - Battery StoragePower plant20 MWPermitted4.8 km
North Humber to High MarnhamTransmission line—Planned43 km
Chesterfield to WillingtonTransmission line—Planned48 km

Grid operator and place

More from Northern Powergrid (Yorkshire) plc

Other grid connections in England

All 3831 grid connections in England, United Kingdom

Data on this page