Battery storage and Solar 45 MW grid connection at Selby Road Hybrid

Battery storage and Solar 45 MW grid connection at Selby Road Hybrid is a planned grid connection in England, United Kingdom, with 45 MW of capacity, connected by Northern Powergrid (Yorkshire) plc.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationEngland (connection site: Selby Road Hybrid)Northern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
StatusPlanned (Accepted To Connect)Northern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
Attached toCamblesforth (via: bsp)Northern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
Capacity45 MWNorthern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
TechnologyBattery storageNorthern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
TechnologySolarNorthern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
Grid operatorNorthern Powergrid (Yorkshire) plcNorthern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
Queue date22 Sept 2023Northern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
Voltage66 kVNorthern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026
Coordinates53.7468, -1.0311Northern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026

Know more about this grid connection, or want an introduction to its grid operator? Ask us.

How it compares

Battery storage and Solar 45 MW grid connection at Selby Road Hybrid is the 699th-largest of 2,533 grid connections in England and the 1,071st-largest of 3,903 in the United Kingdom by capacity; its 45 MW is <0.1% of the 446,745 MW we hold for the United Kingdom. Ranks and totals cover the grid connections in our data that report their capacity, not every one in existence.

WithinRankTotalShare
England699th of 2,533319,370 MW<0.1%
United Kingdom1,071st of 3,903446,745 MW<0.1%
All grid connections in our data4,186th of 7,6161,281,251 MW<0.1%

Nearby

Within 50 km of this grid connection: 477 power plants (126 operating, 4,468 MW), 347 substations and 3 transmission lines, measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.

NameKindSizeStatusDistance
Helios Renewable Energy ProjectPower plant190 MWPermitted1.3 km
Camblesforth Solar FarmPower plant49.9 MWPermitted1.4 km
Drax Bioenergy with Carbon Capture and Storage ProjectPower plant—Permitted2.4 km
Drax PrimarySubstation——2.7 km
CamblesforthSubstation——2.8 km
DraxSubstation——3.0 km
Yorkshire GREENTransmission line—Permitted23 km
North Humber to High MarnhamTransmission line—Planned34 km
Continental Link Multi-Purpose InterconnectorTransmission line—Cancelled41 km

Grid operator and place