(ANM) Roman Road grid connection
(ANM) Roman Road grid connection is a planned grid connection in England, United Kingdom, with 50 MW of capacity, held by Luminous Energy Group Limited.
Facts
Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.
| Fact | Value | Source |
|---|---|---|
| Location | England (connects at Shenfield Grid 132kV) | UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026 |
| Status | Planned (accepted to connect) | UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026 |
| Holder | Luminous Energy Group Limited | UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026 |
| Capacity | 50 MW | UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026 |
| Technology | Solar | UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026 |
| Technology | Battery storage | UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026 |
| Grid operator | Eastern Power Networks plc (UK Power Networks, East England licence area) | UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026 |
| Queue date | 21 Jun 2024 | UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026 |
| Voltage | 132 kV | UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026 |
| Coordinates | 51.6500, 0.3365 | UK Power Networks open data portal · CC BY 4.0 · checked 25 Oct 2026 |
Research on this grid connection and its holder.Who holds it up to the parent company, the project behind it and its connection date, and an introduction to the holder.
How it compares
(ANM) Roman Road grid connection is the 669th-largest of 3,539 grid connections in England and the 964th-largest of 4,870 in the United Kingdom by capacity; its 50 MW is <0.1% of the 467,981 MW we hold for the United Kingdom. Ranks and totals cover the grid connections in our data that report their capacity, not every one in existence.
| Within | Rank | Total | Share |
|---|---|---|---|
| England | 669th of 3,539 | 341,715 MW | <0.1% |
| United Kingdom | 964th of 4,870 | 467,981 MW | <0.1% |
| All grid connections in our data | 4,149th of 8,618 | 1,355,288 MW | <0.1% |
Nearby
Within 50 km of this grid connection: 475 substations, 382 power plants (150 operating, 7,857 MW), 73 data centers (1 operating, 88 MW), 1 AI supercomputer and 1 transmission line, measured from the coordinates in the facts above. The table shows the nearest 9, up to 3 per kind.
| Name | Kind | Size | Status | Distance |
|---|---|---|---|---|
| Hutton Primary 11kV | Substation | — | — | 1.8 km |
| Billericay Solar Farm - Solar Farm | Power plant | 15 MW | Permitted | 2.0 km |
| Shenfield Grid 33kV | Substation | — | — | 2.0 km |
| Hutton Battery Storage (Lower Road) | Power plant | 10 MW | Operating | 2.1 km |
| Brentwood nergy Storage System | Power plant | 49.9 MW | Cancelled | 2.2 km |
| High St Primary 11kV | Substation | — | — | 4.1 km |
| Imperium 315 | Data center | — | — | 12 km |
| NTT London 1 | Data center | — | — | 16 km |
| Fujitsu Data Centre | Data center | — | — | 19 km |
Holder, grid operator and place
- Luminous Energy Group LimitedHolder
- Eastern Power Networks plcGrid operator
- Grid connections in England, United Kingdom4,837
- Grid connections in the United Kingdom6,880
- Battery storage grid connections in the UK1,141
- Solar grid connections in the UK1,755
- The United Kingdom: country profile
- Largest grid connections
More from Luminous Energy Group Limited
- Ironsbottom Solar Farm grid connection30 MW
- Paddock Wood Solar Farm grid connection7.92 MW
- Cattybrook Solar Farm49.9 MW · permitted
- Stow Park Farm, Stow Park - Solar Panels35 MW · planned
- Bracon Ash Solar28.5 MW · under construction
- Llwyndyrys Farm5 MW
Other grid connections in England
- Bute Hydrogen Project 1 grid connection4,800 MW
- Drax BECCS grid connection3,906 MW
- Drax Power Station grid connection3,906 MW
- Bute Hydrogen Project 2 grid connection3,600 MW
- Bute Hydrogen Project 3 grid connection3,600 MW
- Bute Hydrogen Project 5 grid connection3,600 MW
- Bute Hydrogen Project 6 grid connection3,600 MW
- Hinkley Point C grid connection3,340 MW
Data on this page
- California ISO. CAISO queue report, CAISO Privacy and Terms of Use.
- Contains public sector information licensed under the Open Government Licence v3.0. DESNZ Renewable Energy Planning Database (REPD), Open Government Licence v3.0.
- SP Electricity North West, via Northern Powergrid Open Data. SP Electricity North West open data portal, CC BY 4.0.
- ERCOT GIS report. ERCOT GIS report, ERCOT Terms of Use.
- Supported by National Energy SO Open Data. NESO TEC Register, NESO Open Data Licence v1.0.
- Supported by Northern Powergrid Open Data. Northern Powergrid open data portal, Northern Powergrid Open Data Licence v1.0.
- NYISO interconnection queue. NYISO interconnection queue, Free reuse.
- © OpenStreetMap contributors. OpenStreetMap data centers, ODbL 1.0.
- PJM New Services Queue. PJM New Services Queue, Free reuse.
- SP Energy Networks, via Northern Powergrid Open Data. SP Energy Networks open data portal, CC BY 4.0.
- SSEN Distribution. SSEN Distribution data portal, CC BY 4.0.
- UK Power Networks. UK Power Networks open data portal, CC BY 4.0.