Substation · England, United Kingdom
Fourstones 20kV
Fourstones 20kV is a substation in England, United Kingdom, connected by Northern Powergrid (Northeast) plc.
Facts
Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.
| Fact | Value | Source |
|---|---|---|
| Location | England | Northern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026 |
| Grid operator | Northern Powergrid (Northeast) plc | Northern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026 |
| Congestion (offtake) | None (rag: Green) | Northern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026 |
| Congestion (feed-in) | None (rag: Green) | Northern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026 |
| Demand headroom | 20.2 MVA | Northern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026 |
| Generation headroom | 40 MW | Northern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026 |
| Firm capacity | 60 MVA | Northern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026 |
| Level | Gsp | Northern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026 |
| Voltage | 20 kV | Northern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026 |
| Coordinates | 55.0120, -2.1650 | Northern Powergrid open data portal · Northern Powergrid Open Data Licence v1.0 · checked 24 Oct 2026 |
Know more about this substation, or want an introduction to its grid operator? Ask us.
Nearby
Within 50 km of this substation: 153 grid connections (75 operating, 966 MW), measured from the coordinates in the facts above. The table shows the nearest 3.
| Name | Kind | Size | Status | Distance |
|---|---|---|---|---|
| Battery storage and Solar 80 MW grid connection at Fourstones Hybrid | Grid connection | 80 MW | Planned | 1.5 km |
| Battery storage and Solar 112 MW grid connection at Carr Edge Farm BESS | Grid connection | 112 MW | Planned | 2.1 km |
| Biomass 2.5 MW grid connection at Hexham | Grid connection | 2.5 MW | Operating | 6.1 km |
Grid operator and place
More from Northern Powergrid (Northeast) plc
- Annfieldsubstation
- Barrack Roadsubstation
- Bluchersubstation
- Bowesfieldsubstation
- Chirton Grangesubstation
- Coalburnssubstation
- Darlington Centralsubstation
- Darlington Northsubstation
Other substations in England
Data on this page
- Supported by Northern Powergrid Open Data. Northern Powergrid open data portal, Northern Powergrid Open Data Licence v1.0.