Power plant · Carmarthenshire, Wales, United Kingdom

Pont Andrew Solar Farm

Pont Andrew Solar Farm is a power plant in Carmarthenshire, Wales, United Kingdom, with 1.5 MW of capacity, operated by Lightsource Renewable Energy.

Facts

Every value links to its source, and to the source's own record where it has one. Licences and last-checked dates are per row.

FactValueSource
LocationCarmarthenshire (coordinates), WalesDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
AddressLAND AT FORMER CYNHEIDRE SHAFTS 3 & 4, CYNHEIDRE, LLANELLIDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
StatusOperating (operational)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Start year2012DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Permit date22 Apr 2011 (permit S/24069, Town and Country Planning Act, issued by Carmarthenshire)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Application date29 Nov 2010 (reference S/24069, planning authority Carmarthenshire)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Decision date22 Apr 2011 (granted, reference S/24069, planning authority Carmarthenshire)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
OperatorLightsource Renewable EnergyDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Capacity1.5 MWDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
TechnologySolar PhotovoltaicsDESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Area6.7 ha (solar site area)DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026
Coordinates51.7758, -4.1353DESNZ Renewable Energy Planning Database (REPD) · Open Government Licence v3.0 · checked 24 Oct 2026

Research on this power plant and its operator.Who owns it up to the parent company, its grid connection and planning status, and an introduction to the operator.

Request research

Latest events

Dated events about this power plant from official notices and registers, newest first. All recent changes.

  1. Commissioned
  2. Permit granted (planning authority Carmarthenshire, reference S/24069)
  3. Permit applied for (planning authority Carmarthenshire, reference S/24069)

How it compares

Pont Andrew Solar Farm is the 389th-largest of 424 power plants in Wales and the 4,531st-largest of 5,050 in the United Kingdom by capacity; its 1.5 MW is <0.1% of the 115,622 MW we hold for the United Kingdom. Ranks and totals cover the power plants in our data that report their capacity, not every one in existence. Power plants planned, permitted or under construction are ranked apart.

WithinRankTotalShare
Wales389th of 4249,068 MW<0.1%
United Kingdom4,531st of 5,050115,622 MW<0.1%
All power plants in our data11,084th of 12,0321,190,447 MW<0.1%

Timeline

Dated facts about this power plant from its sources, oldest first.

  1. Started operating

Nearby

Within 50 km of this power plant: 1 transmission line and 1 data center, measured from the coordinates in the facts above.

NameKindSizeStatusDistance
Brechfa Forest ConnectionTransmission line—Permitted21 km
CGI DatacenterData center——50 km

Operator and place

More from Lightsource Renewable Energy

Other power plants in Wales

All 616 power plants in Wales, United Kingdom

Data on this page